SITE PICTURES AND PROGRESS
Rhino Maritime Services and Construction OJOTO EROSION SITE PICTURES AND PROGRESS
2
ROAD CONDITION NOVEMBER 2011
Rhino Maritime Services and Construction ROAD CONDITION NOVEMBER 2011 .
3
EARLY STAGE OF EXCAVATION
Rhino Maritime Services and Construction EARLY STAGE OF EXCAVATION
4
Rhino Maritime Services
and Construction November 2011
5
Rhino Maritime Services
and Construction November 2011
6
WORK STARTS INSIDE THE GULLY 22/03/2012.
Rhino Maritime Services and Construction WORK STARTS INSIDE THE GULLY 22/03/2012.
8
Rhino Maritime Services
and Construction
9
28th February Road compacted and blinded ready for final surface dressing. Drain completed down to termination point.
10
2.1 km - Completed Surface Dressed Road & Drain
March 2013 2.1 km - Completed Surface Dressed Road & Drain