Economic Planning Study (EPS) Updates ColumbiaGrid Planning Meeting June 7, 2018
2
Modeling Assumptions for 2033 High Renewable PCM
Outline Modeling Assumptions for 2033 High Renewable PCM WECC 2028 ADS PCM v0.3.2 2018 Water year/Run-Off
3
Modeling Assumptions for 2033
Supply Additions: Waiting on CA preferred renewable additions Reviewing IRP for preferred supply additions Will fill, in as needed, to maintain minimum reserve margin Run 2028 with supply additions Objective: Determine impact of supply additions over PF based PCM Run 2033 with Objective: Potential impact 50% renewable standard in California
4
WECC 2028 ADS PCM PF Based PCM WECC released v0.3.2 on 6/1
A little unserved load exist in PNM and CFE Dump energy exist: WECC working on resolving constraints: primary in CA Bas. Other areas: PGE, PNM, NWMT, PACW, TPWR NW: Jones Canyon or PG&E: Shiloh Wind area Working to identify and resolve any commit/dispatch issues Load updated to 2018 L&R forecast
5
2018 Water Year/Run-off Jan-Jul Run-Off at The Dalles: 121.6 MAF
20% of average MAF Rank 83.1% of 90 year
6
Question: Kevin Harris (503) 943-4932 harris@columbiagrid.org