September 2009 doc.: IEEE /xxxxr0 January 2011 P802.11s timelines Authors: Name Affiliation Address Phone Dee Denteneer Philips HTC 34; 5656 AE Eindhoven, the Netherlands Discuss TGs timelines, in relation to the timelines of REVmb Dee Denteneer (Philips) Menzo Wentink (Qualcomm), Bruce Kraemer, Marvell

2 TGs Timeline, from Doc 11-10/895r6
January 2011 Open Close Fourth recirculation (TGs draft 7.0) 24-Jul-10 12-Aug-10 Professional editing + MEC 30-Sep-10 Pool formation 22-July-10 12-Sep-10 First sponsor ballot 1-Oct-10 1-Nov-10 Second sponsor ballot 13-Dec-10 12-Jan-11 Third sponsor ballot 24-Jan-11 13-Feb-11 Fourth sponsor ballot 1-Mar-11 16-Mar-11 Fifth sponsor ballot 1-Apr-11 16-Apr-11 EC to RevCom Jul-11 RevCom to SB Sep-11 Dee Denteneer (Philips)

3 TGs Timeline, from Doc 11-10/895r6
January 2011 Open Close Fourth recirculation (TGs draft 7.0) 24-Jul-10 12-Aug-10 Professional editing + MEC 30-Sep-10 Pool formation 22-July-10 12-Sep-10 First sponsor ballot 1-Oct-10 1-Nov-10 Second sponsor ballot 13-Dec-10 12-Jan-11 Third sponsor ballot 24-Jan-11 13-Feb-11 Fourth sponsor ballot -> third 1-Mar-11 16-Mar-11 Fifth sponsor ballot -> fourth 1-Apr-11 16-Apr-11 Fifth Sponsor ballot 1-May-11 16-May-11 EC to RevCom Jul-11 RevCom to SB Sep-11 Dee Denteneer (Philips)

4 January 2011 Question Are we bold enough to claim that recirculation 5 is the clean recirculation, or do we need to make changes during Recirculation 5, necessitating another recirculation? In the following, I assume that to be the case Also, I assumed that we do not make a recirculation out of this meeting Also this needs confirmation from the TG Dee Denteneer (Philips)

5 Plan In the following slides we provide a more detailed mapping
January 2011 Plan In the following slides we provide a more detailed mapping Depending on 11s completes before REVmb 11s completes after REVmb; for this case, we assume that REVmb completes its clean recirculation by Oktober 17 Goal: to agree on a timeline for discussion with REVmb and the editors meeting Dee Denteneer (Philips)

6 TGs recirculations; TGs before REVmb
January 2011 TGs recirculations; TGs before REVmb Draft 8.0 recirculation completed January 10, 2011 Draft 8.0 Comment Resolution completed February 17, 2011 Draft 9.0 recirculation completed March 8, 2011 Draft 9.0 Comment Resolution completed March 21, 2011 Draft 10.0 recirculation completed April 5, 2011 Draft 10.0 Comment Resolution completed April 18, 2011 Draft 11.0 recirculation completed May Draft 11.0 Comment Resolution completed May 21, 2011 Draft 11.0 Clean recirculation completed June 6, 2011 Dee Denteneer (Philips)

7 TGs recirculations; TGs after REVmb
January 2011 Draft 8.0 recirculation completed January 10, 2011 Draft 8.0 Comment Resolution completed February 17, 2011 Draft 9.0 recirculation completed March 8, 2011 Draft 9.0 Comment Resolution completed March 21, 2011 Draft 10.0 recirculation completed April 5, 2011 Draft 10.0 Comment Resolution completed April 18, 2011 Draft 11.0 recirculation completed May Draft 11.0 Comment Resolution completed May 21, 2011 Draft 12.0 recirculation completed November 2, 2011 Draft 12.0 Comment Resolution completed November 22, 2011 Draft 12.0 Clean recirculation December 7, 2011 Dee Denteneer (Philips)

8 Scenario 1 January 2011 This corresponds to the following sequence of events, assuming TGs goes before REVmb Scenario 1, current date Recirculations February-May, 2011* Request EC Unconditional Approval to go to Revcom July 2011 Get on September Revcom agenda August/Sept 2011 Revcom approval September 2011 Publication *Note: there is room for some more recirculations to meet the September REVcom agenda Dee Denteneer (Philips)

9 Scenario 2 January 2011 A speed up was suggested, still assuming TGs goes before REVmb, however, this is ok only with the original timeline Scenario 2, sped up date Recirculation (Draft 9) February 2011 Request EC Conditional Approval to go to Revcom March 2011 final recircs, Draft 10 and 11 April-May, 2011* Get on June Revcom agenda May 2011 Revcom approval June 2011 Publication July 2011 *Note: Fitting in two recirculations plus a clean recirc is very tight. Dee Denteneer (Philips)

10 Scenario 3 January 2011 REVmb expects to complete Comment Resolution by 17 Oktober 2011, so if we go after REVmb Scenario 3, 11s after REVmb date Recirculations February-May 2011 REVmb and 11s Request EC Conditional Approval to go to Revcom September 2011 final recirculation REVmb completed 17 Okt 2011* Final recircs 11s 18 Okt. – 7 Dec. 2011** Revcom approval of REVmb November 2011 Revcom approval of 11s February 2012 With this completion date, REVmb gets on the November REVcom agenda; TGs will meet the Feb. 17 deadline to be on the february REVcom agenda Dee Denteneer (Philips)

11 January 2011 Strawpoll Is a time period of 4 months (mid January 2011-mid May 2011) enough to satisfactorily complete the TGs Draft basing ourselves on Yes: 4 No: 0 Abstain: 8 Dee Denteneer (Philips)

12 Conclusion In the best estimates: Background:
January 2011 Conclusion In the best estimates: Waiting for REVmb will delay publication of TGs from September (June) 2011 to February 2012 According to an analysis by Adrian Stephens, waiting for TGs will delay publication of REVmb from November 2011 to publication in February 2012 Background: < Dee Denteneer (Philips)