Cause of Sudden Due in TMS for 6.032 KM – BZA Division
2
Due Overdue as on 02/04/2018 is 6.032 LKM
Km 147/0 – 148/0 DN Line – GDR-VKT Due Overdue as on 02/04/2018 is LKM
3
Checking Asset Register
Km 147/0 – 148/0 DN Line – GDR-VKT
4
Test free period 25% of GMT i.e 880x25% = 200 GMT
Km to = LKM Accumulated GMT For 60Kg - Rail life – 800 GMT Test free period 25% of GMT i.e 880x25% = 200 GMT Annual GMT of GDR-VKT Dn Ln Section = 35.35 Frequency – till Rail GMT attains 200GMT It must be tested for every 40 GMT
5
Km 147/0 – 148/0 DN Line – GDR-VKT Last USFD Inspection Date = 18/05/2017 &19/05/2017 As per AGMT = 35.35 Next due must be 40/35.35=1.13 YEARS Which should be after 412 days then date should be 04/07/18. then why Suddenly it appears on 02/04/18?
6
It appears as Rail Crossed 200GMT and become 202.44
And falls in Need Based concept Testing. Its frequency changed to 3 Months as per AGMT, and Next Due date shown as 18/08/17 suddenly on 02/04/2018