UK Link Technology Refresh
Chris Fears December 2007
2
Progress Since Last Update
OAT – 2 phases Jun-Oct ’07 & Oct-Jan ‘08 OAT1 – machine build confirmation – Completed OAT2 – performance testing, operational schedules, support processes, fall back and recovery etc. – Started Internal penetration testing conducted, 3rd party penetration testing planned UAT : Nov – end Jan : Started Shipper trials : Completed 3rd Full scale trial migration added Detailed implementation planning under way
3
Shipper Trial Update Tests have successfully concluded
File transfer connectivity between the Shipper locations and new UK Link Data Centres has been proven NOM files were successfully received, loaded & processed NMR, COS and MDR files were issued to participants who confirmed the file formats and content was as expected Participants confirmed successful loading and processing of all files issued 1 file was sent to a wrong directory due to a configuration error in IX Lesson - Check file location configurations prior to implementation Lesson - Tightened up the file exchange approval mechanism Delivery receipts successfully received for all files issued from the new system
4
OAT is 80% complete UAT is 88 % complete Testing Updates
Completed back up and fail over tests Scheduler testing planned for 19/12 UAT is 88 % complete Performance testing ongoing – looking good
5
Cut-over and Implementation
Outage still planned at 4 days Detailed implementation planning activities ongoing Looking at cut-over activities and catch-up processing Back-out plans also being drawn up MOD proposal 184 drafted to include: 2 partial non-business days for SPA processing and queries (25th & 26th Feb) 4 days relief from data logger liabilities (24th-27th Feb)
6
Cutover Approach Data cutover
Will start 3 weeks in advance of main cutover, then will require “delta” data updates This will have no effect upon the operational service Final cutover starts 22nd/23rd February 2008 REC invoice to be issued early on Friday 22nd – due dates will be unchanged Other production runs on 22nd will be unchanged Outage start time Start after Datalogger issue on Saturday 23rd confirmed as optimal approach
7
Major Milestones Date Milestone 10/01/08 Mod 184 Approved 14/01/08
Interface Routing Implemented 21/01/08 UAT Completed OAT Completed 27/01/08 Dress Rehearsal Completed 01/02/08 Bulk Data Migration Started 21/02/08 Readiness Verified 23/02/08 Start Outage 25/02/08 Start Catch Up 28/02/08 Complete Catch Up 30/05/08 End of Post Implementation Support
8
Go/No-Go Decision Points
ID Date Input Output G1 10th Jan UKLC Mod184 Approved Industry recognition to proceed G2 11th Jan Interface Plans Agreed Move to early interface implementation G3 22nd Jan UAT and Oat Completed Initiate Bulk Data Migration G4 01ST Feb Dress Rehearsal completed, All plans in place Start pre-cutover activities G5 21st Feb All approvals in place Approval to start G6 23rd Feb Data loggers Complete Start Outage G7 24th Feb Migrations Completed Desk top rollout and reconciliation checks G8 25th Feb 11:00 Data Rec. Completed Release to internal users for screen verification G9 25th Feb 17:00 On Line Verification complete Start batch catch up G10 26th Feb 09:00 Transfer Routes and data validated Release to internal other systems G11 26th Feb 10:00 Files generated and verified Release to Shippers
9
System Impacts System Saturday 23rd Feb Sunday 24th Feb
Monday 25th Feb Tuesday 26th Feb Wed’s 27th Feb Conquest Outage Returns PM and will reflect UK Link As UK Link IAD Will have data as 22nd Will have data as 23rd Will have data as 24th , 25th SP Transfer No Run Run 24th and 25th Run 26th and 27th Data Loggers 23rd Run Run 24th and 25th DN Link
10
Implementation Concerns & Mitigations (1)
Data Corruption IBM conducting a health check on the migration and validation processes Replaced manual checks with scripted , repeatable checks System performance No adverse performance observed during testing All testing done on production sized environments Back Outs As part of the Dress Rehearsal we will practise the back out steps Once we have propagated the data to the systems of others we will be in a “fix forwards” situation
11
Implementation Concerns & Mitigations (2)
Checkpoints The implementation will have a series of go/no-go points identified Expanded the number of health checkpoints during implementation Both time and event driven Will hold files and validate before release Communications Will be using the xoserve web site for general updates Specific updates around the implementation will go to the standard distribution lists (UKLC and Operations) Will use the existing xoserve teams for communications
12
Next Steps IBM to complete assurance of testing and data migration approach Completion of OAT Phase 2 Includes completion of 3rd party penetration testing Progress UAT to completion Finalise Implementation Planning Plan detailed activities for Dress Rehearsal Define and refine back out processes Enhance the go/no go and escalation criteria Finalise catch-up and return to normal operation plan