Presentation is loading. Please wait.

Presentation is loading. Please wait.

Facilities Location, Layout and Planning

Similar presentations


Presentation on theme: "Facilities Location, Layout and Planning"— Presentation transcript:

1 Facilities Location, Layout and Planning

2 FACILITY PLANNING The placement of facility – customers, suppliers, other links in the supply chain Resources Strategy – 99cents Only example Access to customers Government impacts

3 Objectives of Facility Layout
Minimize material handling costs Utilize space efficiently Utilize labor efficiently Eliminate bottlenecks Facilitate communication and interaction between workers, between workers and their supervisors, or between workers and customers Reduce manufacturing cycle time or customer service time

4 Objectives of Facility Layout
Eliminate waste or redundant movement Facilitate the entry, exit, and placement of material, products, or people Incorporate safety and security measures Promote product and service quality Encourage proper maintenance activities Provide a visual control of operations or activities Provide flexibility to adapt to changing conditions Increase capacity

5 Questions on Layout Planning
How should the facility be laid out? Does my layout cause unnecessary movement/excess travel time? Does my work flow in a logical manner? Does size dictate layout or does layout/product flow dictate the size?

6 Basic Types of Layouts Process Layout Product Layout
Machines grouped by process they perform Product Layout Linear arrangement of workstations to produce a specific product Fixed Position Layout Used in projects where the product cannot be moved

7 Manufacturing Process Layout
D G A Receiving and Shipping Assembly Painting Department Lathe Department Milling Department Drilling Department Grinding P

8 Manufacturing Process Layout
D G A Receiving and Shipping Assembly Painting Department Lathe Department Milling Department Drilling Department Grinding P

9 Manufacturing Process Layout
D G A Receiving and Shipping Assembly Painting Department Lathe Department Milling Department Drilling Department Grinding P

10 A Product Layout In Out

11 Fixed-Position Layouts
Typical of projects Equipment, workers, materials, other resources brought to the site Highly skilled labor Often low fixed Typically high variable costs

12 Designing Process Layouts
Minimize material handling costs Block Diagramming Minimize nonadjacent loads Use when quantitative data is available Relationship Diagramming Based on location preference between areas Use when quantitative data is not available

13 Block Diagramming Create load summary chart
Calculate composite (two way) movements Develop trial layouts minimizing number of nonadjacent loads Example

14

15 Relationship Diagramming (Murther’s Grid)
Used when quantitative data is not available Muther’s grid displays preferences Denote location preferences with weighted lines

16 Relationship Diagramming Example
Production Offices Stockroom Shipping and receiving Locker room Toolroom

17 Relationship Diagramming Example
A Absolutely necessary E Especially important I Important O Okay U Unimportant X Undesirable A O U E X I Production Offices Stockroom Shipping and receiving Locker room Toolroom

18 Relationship Diagramming Example
1 Absolutely necessary 2 Especially important 3 Important 4 Okay 5 Unimportant 6 Undesirable 1 4 5 2 6 3 Production Offices Stockroom Shipping and receiving Locker room Toolroom

19

20 Facility Location Models

21 Types Of Facilities Heavy manufacturing Light industry
Auto plants, steel mills, chemical plants Light industry Small components mfg, assembly Warehouse & distribution centers Retail & service

22 Factors in Heavy Manufacturing Location
Construction costs Land costs Raw material and finished goods shipment modes Proximity to raw materials Utilities Labor availability

23 Factors in Light Industry Location
Construction costs Land costs Easily accessible geographic region Education & training capabilities The biggest factor that is different between heavy and light manufacturing is education and training capability of the area. To have high tech type industries you have to have quality education institutions.

24 Factors in Warehouse Location
Transportation costs Proximity to markets (Customers)

25 This is one example of a study to help companies with location analysis

26

27 Service Location Considerations
Labor Cost of Living Real Estate Construction Government Incentives Examples – Amoco, Mass St, Tattoo Parlors, Walgreen’s

28 Global Location Factors
Government stability Government regulations Political and economic systems Economic stability and growth Exchange rates Culture Climate Export import regulations, duties and tariffs Raw material availability Number and proximity of suppliers Transportation and distribution system Labor cost and education Available technology Commercial travel Technical expertise Cross-border trade regulations Group trade agreements

29 Regional Location Factors
Community government Local business regulations Government services Business climate Community services Taxes Availability of sites Financial Services Community inducements Proximity of suppliers Education system

30 Site Location Factors Customer base Construction/ leasing cost
Land cost Site size Transportation Utilities Zoning restrictions Traffic Safety/security Competition Area business climate Income level

31 Location Incentives Tax credits Wal-Mart in Wyandotte
Relaxed government regulation Job training Infrastructure improvement Money

32 Center-of-Gravity Technique
Locate facility at center of geographic area Based on weight and distance traveled Establish grid-map of area Identify coordinates and weights shipped for each location

33 Facility Summary Why is it important? Location analysis
Location Criteria – global, local, regional - education Location and Strategy Location and Customers Layout planning

34 Project Management and Operations

35 Project Management First Essay on Project Management:
1697 – “An Essay Upon Projects” 1959 HBR Article – “The Project Manager” Air Force Manual 1964

36 Project Management In today’s global marketplace, complexity and speed are certainties. In such an environment, a good axiom for project management is, Do It, Do It Right, Do It Right Now. Creating clear direction, efficiency, timely response, and quality outcomes requires project managers who are agile -- adept at change. The associated disciplinary areas are clearly spelled out in the following PMI definition. “Project management is the application of knowledge, skills, tools, and techniques to a broad range of activities in order to meet the requirements of a particular project. Project management is comprised of five Project Management Process Groups – Initiating Processes, Planning Processes, Executing Processes, Monitoring and Controlling Processes, and Closing Processes. Source: Project Management Institute -

37 Elements of Project Management
Project team Individuals from different departments within company Matrix organization Team structure with members from different functional areas depending on skills needed Project manager - Leader of project team Project Charter – high level description of what is to be accomplished in a project and delegates authority to project manager to implement actions to complete project

38 Project Planning Statement of work
Written description of goals, work & time frame of project Activities require labor, resources & time Precedence relationship shows sequential relationship of project activities

39 Elements of Project Planning
Define project objective(s) Identify activities Establish precedence relationships Make time estimates Determine project completion time Compare project schedule objectives Determine resource requirements to meet objective

40 Work Breakdown Structure
Hierarchical organization of work to be done on a project Project broken down into modules Modules subdivided into subcomponents, activities, and tasks Identifies individual tasks, workloads, and resource requirements

41 Project Control All activities identified and included
Completed in proper sequence Resource needs identified Schedule adjusted Maintain schedule and budget Complete on time

42 A Gantt Chart Around since 1914
Popular tool for project scheduling Graph with bar for representing the time for each task Provides visual display of project schedule Also shows slack for activities Amount of time activity can be delayed without delaying project

43 Gantt Charts Gantt described two principles for his charts:
measure activities by the amount of time needed to complete them the space on the chart can be used the represent the amount of the activity that should have been done in that time. Gantt charts were employed on major infrastructure projects including the Hoover Dam and Interstate highway system and still are an important tool in project management.

44 A Gantt Chart Month 0 2 4 6 8 10 | | | | | 1 3 5 7 9 Figure 6.2
| | | | | Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work Month Figure 6.2

45 CPM/PERT Critical Path Method (CPM)
DuPont & Remington-Rand (1956) Deterministic task times Project Eval. & Review Technique (PERT) US Navy, Lockheed Multiple task time estimates

46 PERT/CPM Program Evaluation and Review Technique (PERT): developed in conjunction with the development of the Polaris missile program for submarines – developed by the US Navy with Lockheed as the lead contractor Critical Path Method (CPM): developed through a joint venture between the DuPont Corporation and the Remington Rand Corporation – the original purpose was to monitor and evaluate plant maintenance management projects.

47 Project Network for a House
3 2 1 4 6 7 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house Figure 6.4

48 Critical Path A path is a sequence of connected activities running from start to end node in network The critical path is the path with the longest duration in the network Project cannot be completed in less than the time of the critical path

49 The Critical Path A: 1-2-3-4-6-7 3 + 2 + 0 + 3 + 1 = 9 months
1 4 6 7 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house A: = 9 months B: = 8 months C: = 8 months D: = 7 months

50 The Critical Path 1 2 4 6 7 3 5 Activity Start Times
1 4 6 7 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house 1 2 4 6 7 3 5 Start at 3 months Start at 5 months Finish at 9 months Start at 8 months Activity Start Times Figure 6.6

51 Project Crashing Crashing is reducing project time by expending additional resources Crash time is an amount of time an activity is reduced Crash cost is the cost of reducing the activity time Goal is to reduce project duration at minimum cost

52 Time-Cost Relationship
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs

53 Life Cycle Management Long term view of projects to guide decision making – solutions that provide life time success vice short term Acquisition; development; production; introduction; sustainment; disposal Links system costs to big picture; better use of resources; minimize total cost of ownership

54 Capacity and Aggregate Planning

55 Capacity Outputs: Examples

56 The goal of capacity planning decisions
The capacity of the firm to produce the service or good The processes for providing the service or making the good The layout or arrangement of the work space The design of work processes to enhance productivity

57 Capacity The max output that an organization be capable of producing
Measure a single facility: Design vs. Effective capacity Capacity Utilization: design vs. efficient utilization For systems have more than one facility and flows of product System capacity and bottleneck Improve system capacity

58 Determinants of Effective Capacity
Facilities Human considerations Adding people Increasing employee motivation Operations Improving operating rate of a machine Improving quality of raw materials and components External forces Safety regulations

59 Capacity Utilization Measures how much of the available capacity is actually being used: Always <=1(percentage of usage) Higher the better Denominator: If effective capacity used: efficient utilization If design capacity used: design utilization

60 Aggregate Planning The process of planning the quantity and timing of output over the intermediate range (3-18 months) by adjusting production rate, employment, inventory Master Production Schedule: formalizes the production plan and translates it into specific end item requirements over the short to intermediate horizon

61 Capacity Planning The process of determining the amount of capacity required to produce in the future. May be at the aggregate or product line level Master Production Schedule - anticipated build schedule Time horizon must exceed lead times for materials

62 Capacity Planning Look at lead times, queue times, set up times, run times, wait times, move times Resource availability Material and capacity - should be in synch driven by dispatch list - listing of manufacturing orders in priority sequence - ties to layout planning load profiles - capacity of each section

63 the capacity decisions:
When to add capacity How much capacity to add Where to add capacity What type of capacity to add When to reduce capacity

64 Capacity Planning Rough Cut Capacity Planning - process of converting the master production schedule into requirements for key resources capacity requirements plan - time-phased display of present and future capacity required on all resources based on planned and released orders

65 Capacity Planning Capacity Requirements Planning (CRP) - process of determining in detail the amount of labor and machine resources required to meet production plan RCCP may indicate sufficient capacity but the CRP may indicate insufficient capacity during specific time periods

66 Theory of Constraints Every system has a bottle neck
capacity of the system is constrained by the capacity of the bottle neck increasing capacity at other than bottle neck operations does not increase the overall capacity of the system

67 Theory of Constraints What needs to be changed What to change to
How to make the change happen

68 Theory of Constraints Identify the constraint Subordinate Inertia
Walk the process again inertia of change can create new bottle necks

69 Capacity Planning Establishes overall level of productive resources
Affects lead time responsiveness, cost & competitiveness Determines when and how much to increase capacity

70 Capacity Expansion Volume & certainty of anticipated demand
Strategic objectives for growth Costs of expansion & operation Incremental or one-step expansion

71 Sales and Operations Planning (S&OP)
Brings together all plans for business performed at least once a month Internal and external

72 Adjusting Capacity to Meet Demand
Producing at a constant rate and using inventory to absorb fluctuations in demand (level production) Hiring and firing workers to match demand (chase demand) Maintaining resources for high demand levels Increase or decrease working hours (overtime and undertime) Subcontracting work to other firms Using part-time workers Providing the service or product at a later time period (backordering)

73 Demand Management Shift demand into other periods
Incentives, sales promotions, advertising campaigns Offer product or services with countercyclical demand patterns Partnering with suppliers to reduce information distortion along the supply chain

74 Remedies for Underloads
Acquire more work Pull work ahead that is scheduled for later time periods Reduce normal capacity

75 Remedies for Overloads
Eliminate unnecessary requirements Reroute jobs to alternative machines or work centers Split lots between two or more machines Increase normal capacity Subcontract Increase the efficiency of the operation Push work back to later time periods Revise master schedule

76 Scheduling as part of the Planning Process

77 Scheduling Scheduling is the last step in the planning process?
It is one of the most challenging areas of operations management. Scheduling presents many day-to-day problems for operations managers because of Changes in customer orders Equipment breakdowns Late deliveries from suppliers A myriad of other disruptions

78 Objectives in Scheduling
Meet customer due dates Minimize job lateness Minimize response time Minimize completion time Minimize time in the system Minimize overtime Maximize machine or labor utilization Minimize idle time Minimize work-in-process inventory Efficiency

79 Sequencing Rules FCFS - first-come, first-served
LCFS - last come, first served DDATE - earliest due date CUSTPR - highest customer priority SETUP - similar required setups SLACK - smallest slack CR - critical ratio SPT - shortest processing time LPT - longest processing time

80 Critical Ratio Rule CR considers both time and work remaining
If CR > 1, job ahead of schedule If CR < 1, job behind schedule If CR = 1, job on schedule time remaining due date - today’s date work remaining remaining processing time Ties scheduling to Gantt Chart or PERT/CPM


Download ppt "Facilities Location, Layout and Planning"

Similar presentations


Ads by Google