Download presentation
1
VAPIDRO-ASTE and SMART Mini-Idro tools: hydropower potential assessment and scheme optimization
Project Final Meeting Aosta, Italy May 24th 2012 Julio Alterach, Milena Vergata, Alberto Elli (RSE – Italy)
2
Assessment of the remaining hydropower potential in watercourses
VAPIDRO-ASTE is a free GIS tool, developed by RSE (Italy) that calculates the remaining hydropower potential in a watercourse and the best locations of future plants, considering the Digital Elevation Model, the measured flows and the present withdrawals.
3
VAPIDRO – ASTE tool New project creation
In the frame of the SHARE project, a VAPIDRO-ASTE a customized version was produced. The version will be delivered including the Digital Elevation Model of the Alpine Space area: When creating a new project, the whole map of the Apline Space is shown. The user is able to select and area where to work on. Testing detailed area Alpine Space Area
4
Automatic river generation
VAPIDRO – ASTE tool Area selection, sub-basin computation VAPIDRO-ASTE is able to create automatically the river network, departing from the Digital Elevation Model and the density factor Automatic river generation
5
Watercourse selection
VAPIDRO – ASTE tool Area selection, sub-basin computation Selection of the upstream and downstream points of the study case river. Watercourse selection
6
Installable power and energy
VAPIDRO – ASTE Installable power and energy Energy (kWh/year) It is possible to view the discharge, energy and power tables an charts in reference to the selected river. The “x” axis is the progressive distance measured from the closure. Structural lenght Power (kW)
7
Automatic sub-basin calculation Withdrawals and restitutions
VAPIDRO – ASTE tool Basins, Discharges, withdrawals and restitutions The higher the number of sub-basins, the better the definition of watercourse results (discharge, energy, power). Automatic sub-basin calculation Withdrawals and restitutions Discharges (Measured or natural) Withdrawals Restitutions
8
Installable Power (kW)
Installable power in a GIS map VAPIDRO ASTE is able to visualize the results on GIS, as a map with a coloured scale (heads, energy and power, cost, benefits, financial parameters) Installable Power (kW)
9
Benefit/Cost relationship in a GIS map
10
Hydropower Exploitation
VAPIDRO – ASTE tool Hydropower Exploitation Where to locate the best position of the intake powerhouse system to exploit the residual hydropower potential?
11
Hydropower Exploitation
VAPIDRO – ASTE tool Hydropower Exploitation VAPIDRO Hydropower Optimization Tool: tables and charts
12
Hydropower Exploitation
VAPIDRO – ASTE tool Hydropower Exploitation VAPIDRO Hydropower Optimization Tool: plants in the Map Intake Intake Intake Intake Intake Powerhouse Powerhouse Powerhouse Powerhouse Powerhouse
13
SMART Mini-Idro, SHARE customized version
SMART Mini-Idro is a tool for technical and economical evaluation of mini hydro power plants Evaluates the energy production, benefits and financial aspects Supports the pre-feasibility project analysis Used in the frame of the SHARE project
14
SMART Mini-Idro, SHARE customized version
The following chart shows the composition and relationship of the SMART Mini-Idro modules
15
SMART Mini-Idro, SHARE customized version
SMART Mini-Idro allows the input of the flow duration curve and considers the minimum environmental flow. Calculates the Power duration curve as function of the efficiencies and types of the selected turbine.
16
SMART Mini-Idro, SHARE customized version
SMART Mini-Idro calculates the costs of the plant based on correlation curves, the income from the sale of energy produced and the financial parameters:
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.