FMS Repair Work: Summary
Restacking work nearly completed Small Cells: 100% complete (476/476) Large Cells: 73% complete (572/788) Re-cabling 100% complete Survey Completed Reconstructing magnetic shielding/light-tight box Next week: testing of cable map for HV & signals Gluing
2
Stacking Nearly Complete
Dmtri Kalinkin Grant Webb Sam Heppelmann Ivan Esteban Mriganka Mondal
3
Problems 216 Large Cells Left to complete 34 old FMS Cells
(216-34=182) 40-50 from PSU next week (182-50=132) 12 bases available (132-12=120) Need 10 magnetic shields Cabling/Stacking 1 week work Movement of pole pieces damaged fibers/ethernet Noticed cracking in single small lead glass/north side North/South -7mm difference