1
1 Sub-Group Message Standardisation Activity report to the AG T2S Project Team European Central Bank Bucarest, 30 June 2011
2
2 Overview Change requests to the AG: follow-up Review of messages developed Change requests to ISO
3
3 SGMS March change requests to AG – follow-up See agenda item 7.1
4
4 Message development 19 messages received from 4CB since March for review. 18 are pillar III: Queries, Responses and Reports needed for T2S Despite slight delay in reception (2.5 weeks), SGMS feedback on time for the UDFS 1.2 contribution SGMS Review complete.
5
5 Maintenance requests to ISO 8 maintenance requests were submitted to the ISO Registration Authority on 31May 2011 Next steps: –Maintenance Working Group –Securities Standards Evaluation Group
6
6 THANK YOU