Fourth Quarter Performance Report
2017/18 Mr. M. Tshangana Director-General
2
Presentation Outline Progress on Implementation of the Departmental Annual Performance Plan - Quarter 4 Targets Financial Report including Human Settlements Development Grant and Urban Settlements Development Grant Challenges and Recommendations
3
Programme 1: Administration: Compliance to Statutory Matters
Target achieved and includes but not limited to : Tabling dates observed and adhered to (2018/19 APP) Interim Financial Statements developed and submitted as per the schedule Estimates of National Expenditure submitted, approved and published Departmental Procurement plans submitted and approved. Adherence to the MPAT process and the Department was rated fully compliant on PMDS, recruitment and retention, anticorruption and ethics and being smart in monitoring and disposal management A total of 93,5% of valid invoices paid within 30 days - Unresolved invoice discrepancies, delays in submission of invoices; system error in respect of processing the transaction successfully. The personnel was again reminded by means of supply chain circulars to submit invoices on time. Suppliers were requested to submit invoices to the Supply Chain Management and each order stamped Unqualified Audit Report with matter of emphasis on financial information and material findings on predetermined objectives - Unavailability of source documentation for title deeds backlog eradication at the time of audit – Clear need to establish proper systems and processes to collate and verify information
4
Programme 1: Administration: Compliance to Statutory Matters
100% Adherence to the Schedules of Parliament, Cabinet, FOSAD and Management 63 % implementation of the approved internal audit plan. This mainly due to capacity constraints, non-compliance to the agreed audit timeframes or audit requirements by the auditee, delayed appointment of service providers, reprioritisation. Audits completed are: Review of the Interim Financial Statements of Quarter 3 System review of NHNR Follow up audits – IT Governance Quarterly Performance Information Review of Quarter 3 Performance audit on technical capacity development programme 89% implementation of the approved Departmental Anti-Fraud and Corruption Plan. The following are some of the milestones that were accomplished: Monitor and report quarterly progress on the implementation of the Anti-Fraud and Corruption Policies Fraud Prevention Plan Facilitate anti-corruption awareness campaigns to suppliers and external stakeholders. Monitor action taken to implement recommendations relating to reported fraud incidents 100% compliance to Promotion of Access to Information Act (PAIA) provisions and the 2017/18 PAIA Manual was printed in 3 official languages and distributed
5
Programme 1: Administration: Compliance to Statutory Matters
81% implementation of the HR Plan. Progress made on various milestones and includes filling of vacant posts. There is a total of 644 posts which are all funded. Out of the 644 funded posts, 597 is filled. The lower level posts i.e Secretaries, Personal Assistants, Office Managers and Cleaners have been put on hold whist prioritising senior vacant posts. Staff Development (Training) - The following training and development interventions were done during 3rd quarter - Skills Prgrammes (NQF-Aligned) Short Courses (NON NQF-Aligned) 98% availability of HSS Database Systems to provinces. Maintenance was conducted as required 85% availability of IT support services. This is due to unplanned excessive downtime from the service provider 100% implementation of the approved communication strategy
6
Progress on the Development of Legislation
Progresses made regarding the development of the comprehensive legislation relates to presentation of the following: Property Practitioner's Bill to Cabinet Sub-Committee for human settlements on 22 November 2017. HLAMDA bill to the DPSA and the department obtained a preliminary legal opinion from the Office of the State Law Adviser (OCSLA) dated 20 November 2017 as well as the memorandum on the object of the Bill. Housing Consumer Protection bill, 2017 to the Technical Working Group (TWG) on 21 November 2017 and it was supported to be tabled at the Social Protection, Community and Human Development (SPCHD) Cluster. Development of a draft policy framework for human settlements legislation on amending the Consumer Protection developed
7
Progress on the Development of Legislation
Human Settlements Development Bank Bill, approved Policy submitted to the Service Provider to align it with the Policy and a Business Case. Rental Act - The Department obtained the second draft regulations which were circulated to the Steering Committee for comments and inputs. PIE Bill - the Department together with the Department of Monitoring and Evaluation (DPME) conducted a Socio-Economic Impact Assessment (SEIAS) phase 1 on 07 December 2017. Human Settlements Bill - The submission of the Terms of Reference for the appointment of a service provider to draft a human settlements Bill which will repeal the Housing Act 107, 1997 (Act No. 107 of 1997) is waiting for approval.
8
Programme Delivery The Human Settlements Department had interventions within the 22 mining towns providing support on the revitalisation of distressed mining communities - Greater Tubatse, Fetakgomo, Elias Motsoaledi, Lephalale, Rusternberg, Madibeng, Moses Kotane, Matlosana, eMalahleni, Steve Tshwete, Matjahabeng, Merafong, Mogale City, Randfontein, Westonaria, Gamagara, Tsantsabane, Kgatelopele, Gasegonyana, Thabazimbi, Kgetleng Rivier and Thabatshweu The catalytic projects are at various stages of implementation - Thirty four (34 catalytic projects) were implemented. 100% of projects under implementation monitored and verified (HSDG and USDG) Terms of Reference approved by Bid Adjudication Committee on 8 March 2018 for advertising towards conducting the UISP evaluation
9
Progress on Delivery Targets
Quarter 4 Target Actual Performance (Variance) pre-and post-1994 title deeds issued pre-and post-1994 title deeds issued 38 391 The management of Title Deeds Restoration project has been institutionalised Project Managers being appointed to support National intervention measures title deeds for new subsidy houses issued 0 title deeds for new developments houses 23 300 3 000 Hectares of well-located land acquired, rezoned, and released for new developments About 1543,202 Hectares of well-located land was acquired and released for new developments and 840,4147 Hectares of well-located land rezoned 1456, 798 Hectares of land not acquired and released not rezoned
10
Progress on Delivery Targets
Quarter 4 Target Actual Performance (Variance) 75 Informal settlement upgrading plans developed 9 informal settlement upgrading plans developed 66 informal settlement upgrading plans not developed Delay in the appointment of Professional Resource Teams (PRT's) households in informal settlements upgraded households in informal settlements upgraded HSDG - 23 128 and USDG 3 945 households in informal settlements not upgraded 600 non-statutory Military Veterans housed 192 Military Veterans houses delivered 408 Military Veterans not housed
11
Progress on Delivery Targets
Quarter 4 Target Actual Performance (Variance) Seven Provinces and six Metros supported in the implementation of PHP Policy Supported eight (8) Provinces and six (6) Metros. Western Cape, Eastern Cape, KwaZulu Natal, Mpumalanga, North West, Gauteng, Free State, Limpopo) and City of Cape Town, Nelson Mandela Bay Metro, Mangaung, City of Johannesburg, Ethekwini, Ekurhuleni supported in the implementation of PHP Policy individual units for subsidy housing submarket provided individual units for subsidy housing submarket provided individual units for subsidy housing submarket not provided 2 730 private affordable rental housing opportunities delivered 489 private affordable rental opportunities delivered 2 241 private affordable rental housing opportunities not delivered 2 000 of Social Housing units delivered 542 Social Housing units delivered 1 458 Social Housing units not delivered
12
Progress on Delivery Targets
Quarter 4 Target Actual Performance (Variance) 600 Community Residential Units (CRU) delivered 132 Community Residential units (CRU) delivered 468 Community Residential Units (CRU) Not Achieved 1 500 Finance Linked Individual Subsidy Programme (FLISP) subsidies allocated to approved beneficiaries 663 FLISP subsidies allocated to approve beneficiaries. 837
13
Progress on Transformation Targets
8.09 per cent of the USDG construction budget allocated to Women and Youth Contractors 10.42 per cent of the HSDG construction budget allocated to Women and Youth Contractors Four hundred and three (403) practitioners were trained on Land and Property Spatial Information System. This is an online web based land system that assist and allow practitioners to view, track, verify and identify land and property information. Forty five (45) students have been supported through the scholarship programme including tuition, accommodation, text books, meals, stipends and placements
14
Entities’ Performance
Integration of the three entities into a single DFI is in progress – One compliance approval is outstanding. The Department has analyzed the financial, non-financial and risk management elements of the second draft plans The Human Settlements Entities Strategic and Annual Performance Plans were tabled within the required time frames
15
MTSF Implementation Progress As At 31 March 2018
MTSF TARGET 2019 Performance 1 April 2014 to 31 December 2017 MTSF Performance up to 31 March 2018 additional households living in adequate housing through the subsidy and affordable housing segments (annual target ) (65.3%) Variance = 750 000 households in informal settlements provided with upgraded access to basic services(individual access or shared access) by 2019 (74.03%) Variance = NUSP to assist Municipalities with the upgrading of informal settlements by assessment of current status and development of settlement upgrading plans: Target: informal settlements 1536 Informal settlements assessed 883 Settlements upgrading plans developed Variance = 664 Variance = 1 317 individual units for subsidy housing submarket provided by 2019 (annual target ) (81.8%) Variance = Increase in the volume of home loans granted by private sector and DFI’s to households in the affordable housing market and the creation of new units loans (includes incremental loans) Representing new units: units (54,3%) Variance = 1 700 Non-Statutory Military Veterans adequately housed 480 1220
16
MTSF Implementation Progress As At 31 March 2018
MTSF Target 2019 Performance 1 April 2014 to 31 December 2017 MTSF Performance up to 31 March 2018 of affordable rental housing opportunities provided CRU = State – led = Affordable Private Rental = CRU: 5 732 State-led: Private: CRU (63.9%) Variance = 3 606 State-led: (43.9%) Variance = Private: (77.1%) Variance = 5 718 ( title deeds issued to new homeowners in the subsidy submarket and backlog eradicated (New Developments): (Backlog pre- and post- 1994: (New Developments): (19.7%) Variance = (29.9%) Variance = of hectares of well-located land rezoned and released for new developments targeting poor and lower middle income households ha ha (164.1%) Variance = NHBRC enrolments 548 projects representing units 614 projects representing units
18
Expenditure by Programme - 31 March 2018
Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 7 012 44 293 90.5% 2. Human Settlements Policy, Strategy and Planning 31 99 854 11 399 89.8% 3. Programme Delivery Support 12 559 48 572 76.3% 4. Housing Development Finance - 2 951 100.0% Total 19 601 99.7%
19
Expenditure by Economic Classification 31 March 2018
Total Allocation Commitments Expenditure Variance % Spent Compensation of employees - 37 318 90% Goods and services 18 920 63 306 83% Interest Paid 0% Payments For Financial Assets 9 100% Transfers and subsidies 970 Payments for capital assets 24 193 681 18 580 5 613 77% Total 19 601
20
Operational Expenditure by Programme - 31 March 2018
Total Allocation R' 000 Commitments Expenditure Variance % Spent 1. Administration 7 012 44 239 90% 2. Human Settlements Policy, Strategy and Planning 96 471 31 85 985 10 486 89% 3. Programme Delivery Support 12 559 48 569 75% 4. Housing Development Finance 28 639 - 25 688 2 951 Total 19 601 86%
21
Transfer Payments: 31 March 2018
Total Allocation Transferred Variance % Transferred Grants - 100% Human Settlements Development Grant Urban Settlements Development Grant Entities Social Housing Regulatory Authority: Operational 46 815 Social Housing Regulatory Authority: Institutional Investment 20 490 Social Housing Regulatory Authority: Restructuring Capital Grant Social Housing Regulatory Authority: Regulations 8 000 Community Schemes Ombuds Services 29 400 Housing Development Agency Departmental Transfers 25 621 24 651 970 96% Scholarship Programme 9 871 9 869 2 UN Habitat 2 121 Households 1 789 1 728 61 97% CSIR 11 840 10 933 907 92% Payments for financial assets National Housing Finance Corporation Rural Housing loan Fund 50 000 Total
22
Human Settlements Development Grant (HSDG) Expenditure Performance As At 31 March 2018
23
Human Settlements Development Grant Expenditure (HSDG) Performance as at 31 March 2018
Year to Date (01 April 2017 – 31 March 2018) Provinces Spent by Provinces Unspent against Total available % Spent against Total Available Unspent as % of Total Available Voted Funds Stopped/Reallocated Funds Roll Over from 2016/17 Total Available R'000 Eastern Cape - 1 100 Free State 323 Gauteng 43 705 98 2 KwaZulu-Natal 1 372 Limpopo 84 968 622 Mpumalanga 11 888 Northern Cape 8 973 32 402 94 6 North West 26 841 99 Western Cape Total
25
Delivery Targets % Performance on Delivery (April 2017 – March 2018)
NOTE: Targets have been adjusted upwards for KZN (+566 Sites & Units), MP (+ 930Units), NC (+326 Sites & 216 Units) to take additional allocations into account, GP’s was adjusted downwards ( Sites & -286 Units) & its reported delivery for Units adjusted upwards (+172) to ; LP & NW Targets have NOT been adjusted downwards due to unavailability of the revised targets. Note: 2017/18 delivery figures are up to end March 2018 and are preliminary. 12/4/2018
26
Note: 2017/18 delivery figures are up to end March 2018 and are preliminary.
12/4/2018
27
Eastern Cape Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 1 928 33 922 Wall Plate 1 833 32 507 Roof 1 202 25 159 Finishes 2 808 22 167 TOTAL 7 771
28
Free State Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 411 11 328 Wall Plate 312 9 893 Finishes 330 21 579 TOTAL 1 053 42 800
29
Gauteng Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 1 030 52 930 Wall Plate 1 297 33 795 Roof 732 TOTAL 3 059
30
KwaZulu-Natal Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 2 223 49 327 Wall Plate 2 566 85 407 Roof 526 11 672 TOTAL 5 315
31
Limpopo Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 1651 41 571 Wall Plate 1162 38 342 TOTAL 2 813 79 913
32
Mpumalanga Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 845 18 149 Wall Plate 1 145 35 107 Roof 1 081 24 768 Finishes 1 526 46 689 TOTAL 4 597
33
Northern Cape Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 179 2 370 Wall Plate 200 9 000 Roof 100 4 272 TOTAL 505 15 642
34
North West Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 1 526 85 534 Wall Plate 1 901 Roof 2 232 TOTAL 5 659
35
Western Cape Level Of Construction Number Of Structures AMOUNT R'000
Foundation/ Slabs Completed 225 5 625 Wall Plate 238 14 280 Roof 366 34 770 TOTAL 829 54 675
36
Expenditure Correlation against Milestones
Province Total Available Total Spent Spent on Sites & Units Other Milestone WIP % spent vs. Other Milestone % spent vs. WIP % spent on Deliverables % Delivery Peformance R'000 Eastern Cape 22 5 73 107 Free State 83 870 42 800 7 4 89 84 Gauteng 16 81 49 KwaZulu-Natal 14 82 96 Limpopo 87 102 79 913 6 87 80 Mpumalanga 10 8 109 Northern Cape 15 642 36 3 60 83 North West 13 27 57 Western Cape 54 675 2 88 Total 79 77
37
Work In Progress - Incomplete Top Structures
Province Foundations Wall Plate Roofing Finishes Total Output Amount R'000 Eastern Cape 1 928 33 922 1 833 32 507 1 202 25 159 2 808 22 167 Free State 411 11 328 312 9 893 - 330 21 579 42 800 Gauteng 1 030 52 930 1 297 33 795 732 KwaZulu-Natal 2 223 49 327 2 566 85 407 526 11 672 Limpopo 1 651 41 571 1 162 38 342 79 913 Mpumalanga 845 18 149 1 145 35 107 1 081 24 768 1 526 46 689 Northern Cape 179 2 370 200 9 000 100 4 272 15 642 North West 85 534 1 901 2 232 Western Cape 225 5 625 238 14 280 366 34 770 54 675 10 018 10 654 6 239 4 664 90 435
38
Mining Towns Province Mining Towns as at 31 March 2018 Area
Annual Targets Delivery Performance Sites Units Other Funds Allocated (Gazetted) Funds Allocated (As per BP Expenditure R'000 Free State Matjhabeng 1 300 279 - 83 100 127 115 79 691 Moqhaka 15 193 35 519 Total 1 315 472 Gauteng Merafong City 300 1 253 48 500 1 304 91 201 Rand West City 2 282 1 235 60 100 6 Mogale City 400 2 491 20 000 2 982 4 979 1 310 Limpopo Thabazimbi 412 212 22 200 36 835 552 50 346 Elias Motsoaledi 700 507 10 100 71 636 371 34 207 Lephalale 500 805 14 600 63 61 287 LIM 476 600 34 400 55 462 248 23 531 1 612 2 124 81 300 682
39
Mining Towns Province Mining Towns as at 31 March 2018 Area
Annual Targets Delivery Performance Sites Units Other Funds Allocated (Gazetted) Funds Allocated (As per BP Expenditure R'000 Mpumalanga Emalahleni 1 500 1 140 - 79 200 511 Steve Tshwete 245 565 31 400 78 394 360 92 367 Thaba- Chweu 810 23 200 87 255 196 70 841 Total 1 745 2 515 3 000 1 067 Northern Cape Tsantsabane 8 700 12 000 7 719 Ga-Segonyana 300 102 10 300 24 384 204 28 33 876 Gamagara 8 500 12 903 37 838 Kgatelopele 1 700 5 200 5 858 600 29 200 54 487 85 291 North West Rustenburg 1 433 1 584 83 400 54 31 427 Madibeng 167 721 153 63 147 Kgetleng River 414 26 400 54 515 114 49 085 Moses Kotane 875 93 300 975 312 City of Matlosana 1 296 932 456 2 896 526 1 089 Grand Total 11 150 5 718 4 731 4 303 115
40
Urban Settlements Development Grant (USDG) Expenditure Performance As At 31 March 2018
41
Urban Settlements Development Grant Expenditure (USDG) Performance as at 31 March 2018
Metros Voted Funds Roll Over from 2016/17 Stopped/Reallocated Funds Total Available Year to date (1 July- 31 March 2018) Spent by municipality Variance Spent vs. Total Available % Spent vs. Total Available % Unspent vs. Total Available R'000 Buffalo City - 49,5 50,5 Nelson Mandela Bay 45,6 54,4 Mangaung 82 229 Ekurhuleni 12 098 46,9 53,1 City of Johannesburg 48,5 51,5 City of Tshwane eThekwini 45,3 54,7 City of Cape Town 58 501 42,6 57,4 Total 46,1 53,9
43
Buffalo City Performance
Description Adjusted Budget Spent by Municipality Unspent funds R'000 Human Settlements 47 754 93 641 Roads and Storm water 66 299 Transport Planning 71 550 28 430 43 120 Water 90 000 66 003 23 997 Sanitation 32 345 Electricity 13 000 3 048 9 952 Waste Management/ Refuse 21 162 - Social and Economic Amenities 26 400 13 931 12 469 EPMO-Project Management Funding 23 044 17 557 5 487 Reallocated Funds Total THANK YOU THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - Expenditure 16/17 1 005 24 132 79 639 73 543 51 371 25 362 19 541 56 756 Variance Cummulative Variance 52 119 77 517
44
Nelson Mandela Bay Performance
THANK YOU Description Allocated Budget Spent by Municipality Unspent funds R'000 Human Settlements Roads, Storm water and Transportation 85 500 73 096 12 404 Water Service 83 319 Sanitation Service Electricity & Energy 17 100 22 100 5 000 Public Health (Social amenities) 5 700 - Reallocated Funds Total THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - Expenditure 16/17 27 793 66 276 47 233 62 149 62 116 79 186 49 633 31 290 71 966 Variance Cummulative Variance 93 698 31 549 84 614
45
THANK YOU MANGAUNG PERFORMANCE Mangaung Performance Description
Adjusted Budget Spent by Municipality Unspent funds R'000 Human Settlements and Housing 3 318 Roads and Storm water 90 899 Water Services 89 172 74 547 Sanitation 59 851 Waste management 6 404 3 271 3 133 Social Amenities 58 845 7 679 51 166 Mangaung Metro Opex 17 650 - Reallocated Funds Total THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - 82 229 Expenditure 17/18 43 942 70 492 79 982 36 840 91 444 25 260 17 240 65 062 Variance 2 247 34 938 Cumulative Variance
46
Ekurhuleni Performance
THANK YOU Description Adjusted Budget Spent by Municipality Unspent funds R'000 Land Banking & Property acquisition - Human Settlements Roads and Stormwater 85 379 56 971 Water and Sanitation 70 828 Electricity 54 732 Waste Management - Refuse Removal 52 000 45 661 6 339 OPSCAP - Capacity 31 752 15 075 16 677 Reallocated Funds Total THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - 12 098 Expenditure 16/17 62 623 79 587 84 782 Variance Cumulative Variance
47
City Of Johannesburg Performance
Description Adjusted Budget Spent by Municipality Unspent funds R'000 Land acquisition 2 950 750 2 200 Housing Roads Water 61 718 69 294 Sanitation 49 845 64 326 Electricity 15 329 Social ameneties 68 948 18 634 50 314 Stopped and reallocated funds - Total THANK YOU THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - Expenditure 16/17 821 9 924 74 391 91 376 40 108 84 481 Variance -9 924 Cummulative Variance
48
City Of Tshwane Performance
Description Adjusted Budget Spent by Municipality Unspent funds R'000 Housing & Human Settlements Roads and Transport 59 630 96 074 Water & Sanitation 55 094 Energy and Electricity 3% USDG OPSCAP 48 493 48 492 1 Total THANK YOU THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - Expenditure 16/17 15 439 25 255 97 103 72 812 56 606 Variance Cummulative Variance
49
Ethekwini Performance
Description Adjusted Budget Spent by Municipality Unspent funds R'000 Housing Roads and storm water 75 246 Ethekwini Transport Authority 29 162 1 741 27 421 Water Sanitation 86 670 Socio Economic Amenities 46 018 Solid Waste/ Refuse 24 995 228 24 767 Office of the City Manager - 3% USDG OPSCAP 14 000 13 633 367 Total THANK YOU THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - Expenditure 16/17 55 742 74 690 89 830 64 774 Variance Cumulative Variance
50
City Of Cape Town Performance
Description Adjusted Budget Spent by Municipality Unspent funds R'000 Human Settlements 1 550 - Roads and Storm water 73 123 Transport Planning Water Sanitation 42 428 95 932 Electricity 24 419 84 338 Waste Management/ Refuse Social and Economic Amenities 41 175 23 783 17 392 EPMO-Project Management Funding Total THANK YOU THANK YOU 2017/18 July August September October November December January February March April May June Total Payment Schedule - 58 501 83 069 Expenditure 16/17 4 651 59 199 47 801 63 949 85 241 13 687 86 065 Variance -5 448 -2 172 Cummulative Variance 38 669
51
THANK YOU Matter To Note
An Intervention Task Team formed to address delivery and implementation concerns around Gauteng Province and its Metropolitan Municipalities. THANK YOU
52
Challenges and Recommendations
Slow delivery on the MTSF targets. The targets may not be accomplished by the end of the cycle due to poor performance by provinces, unsatisfactory intersectoral collaborations and delayed procurement processes. Need to ensure variances from the 2014 MTSF targets are accounted for mainly through the sector APP’s – Customised Indicators have been issued. Conflicting sources of information in the sector results in audit queries – Sectoral ICT Forum Established with Entities. Need mechanisms for a single reliable and credible source of information. Mechanisms for a comprehensive reporting is implemented. Need to ensure that all planned measures have credible verification standards and processes.
53
Challenges and Recommendations
Lack or insufficient integration of planning, budgeting and reporting processes across the sector has negative impact in the ultimate delivery to customers or key stakeholders. Overall current performance of the organisation (52%) is still at the margin and this is a concern to the organisation – Improved perfromance contracting to be undertaken. Issues of capacity are being addressed Lack or insufficient collaboration in the sector is attended to through quarterly reviews and the delays in procurement processes is addressed through a panel of resources. Need to ensure that organisational processes and procedures are effective and support the functioning of the organisation as a whole – Revised Organisational Structure, Improved Compliance and Introduction of Mandatory Standard Operating Procedures
54
“We have come a long way – Celebrating 20 Years of Freedom!”
Thank You “We have come a long way – Celebrating 20 Years of Freedom!”