Presentation is loading. Please wait.

Presentation is loading. Please wait.

TDAQ commissioning and status Stephen Hillier, on behalf of TDAQ

Similar presentations


Presentation on theme: "TDAQ commissioning and status Stephen Hillier, on behalf of TDAQ"— Presentation transcript:

1 TDAQ commissioning and status Stephen Hillier, on behalf of TDAQ
System Overview Level-1 Trigger HLT infrastructure DAQ infrastructure DAQ software Commissioning Runs ATLAS Control Room during a TDAQ technical run Everything under control! February 12th, 2008 TDAQ commissioning and status

2 Trigger/DAQ architecture
Detector Front End Electronics (Detector responsibility) Detector RODs Level-1 Trigger Custom Pipelined Hardware Region of Interest Builder Custom Hardware Readout System Custom built buffers in ROS PC farm High-Level Trigger Large PC farm High data bandwidth Dedicated ‘Data’ Network Event Building More PC farms on ‘data’ network DAQ software – control, configuration, monitoring (control network) February 12th, 2008 TDAQ commissioning and status

3 TDAQ commissioning and status
Level-1 Trigger System Three major systems Calorimeter Trigger Muon Trigger Central Trigger Processor (CTP) Other triggers and signals also integrated by CTP Minimum bias Luminosity triggers Beam Pick-up CTP distributes all timing information February 12th, 2008 TDAQ commissioning and status

4 Central Trigger Processor (CTP)
Core CTP available since 2006 Installation now complete New trigger inputs added as they come online Essential for detector commissioning Continuous heavy demand, hence introduction of… Local Trigger Processors Interfaces (LTPi) Allow flexible subdetector local triggering across multiple LTPs 30 modules produced, 5 tested Installation architecture planned for ‘Calorimeter Loops’ Disscussion of ID and muon usage required Documentation and software available February 12th, 2008 TDAQ commissioning and status

5 Level-1 Calorimeter Trigger
Installation in USA15 completed in December 2007 Almost 300 complex custom modules Plus many simpler ones Spread over 10 racks Over 3000 cables laid ~800 thick analogue electrical ~2000 thin digital electrical ~400 optical fibres Commissioning with Calorimeters well underway In M3, M4, M5 Dedicated ‘Calorimeter’ weeks Jet triggers already used, electron/gamma/tau now ready February 12th, 2008 TDAQ commissioning and status

6 TDAQ commissioning and status
Level-1 Muon Trigger On-Detector Electronics Essentially complete But Power Supply delivery is slow Off-Detector Electronics RODs, sector logic etc Complete by end March CTP interface components available Cables, Fibres almost finished February 12th, 2008 TDAQ commissioning and status

7 Level-1 Trigger Commissioning
Calorimeter trigger signals need thorough testing before access disappears Probably end of April About half tested so far Muon trigger commissioning currently done sector by sector Availability of gas and power supplies Timing needs to be addressed Require all triggers to have same timing w.r.t. (non-existent) bunch-crossing The complete system – calo, muon - is rarely (or rather never) available Timing workshop, 11th March HAD Correlation b/w Trigger Tower (Level-1Calo) and Tile Energy Correlation b/w hits in RPC and MDT February 12th, 2008 TDAQ commissioning and status

8 Region of Interest Builder
Installed and working for a long time Takes 8 inputs 1 CTP 1 Muon Trigger 6 Calo Trigger Region of Interest outputs tested in commissioning runs February 12th, 2008 TDAQ commissioning and status

9 High Level Trigger Infrastructure
HLT nodes consist of: Level-2 Supervisors Level-2 Processing Nodes Event Filter Nodes Assignment of roles flexible eg in M5 64*Level-2, 96*EF Granularity of rack Currently 5 racks of PCs >150 nodes 1U rack mounted dual quad core Regularly used in commissioning runs More to come in next three months Expansion to 830 nodes 35% of foreseen system Rapid installation (3 racks per week) February 12th, 2008 TDAQ commissioning and status

10 High Level Trigger Algorithms
HLT algorithm integration tested in ‘technical runs’ Week long and 24 hour Also Mx weeks Performance and timing studies See talk by Frank Winklmeier (this afternoon) February 12th, 2008 TDAQ commissioning and status

11 Network Infrastructure
Two vital, fast networks Data network Dedicated data transport Control network Responsive configuration and monitoring Network expansion in January 2008 Added second control and data core Data core not yet connected to ROSes February 12th, 2008 TDAQ commissioning and status

12 TDAQ commissioning and status
DAQ infrastructure Dataflow view of TDAQ infrastructure: Underground Surface Detectors Permanent Storage Readout Drivers Sub Farm Output Dedicated Optical Links Data Flow Manager Readout System Node Readout Buffers Sub Farm Input Data Network February 12th, 2008 TDAQ commissioning and status

13 TDAQ commissioning and status
Readout System (ROS) Detector Readout Drivers feed Readout Buffers (ROBINs) via 1592 Readout Links All originally foreseen links installed A few more needed for forward detectors ROBINs located in 149 ROS PCs All installed and tested in detector commissioning and technical runs Plus 4 ‘hot’ spares Fast network interfaces to data network February 12th, 2008 TDAQ commissioning and status

14 Sub-Farm Input and Output
Sub Farm Inputs perform Event Building Only on Level-2 selected events Prepare events for Event Filter 32 PCs available and used Event building at ~3kHz (event size 1.5 Mbyte) Sub Farm Outputs write events to disk On Event Filter selected events Write to separate streams 6 available (final number) 300 Mbyte/s to computer centre February 12th, 2008 TDAQ commissioning and status

15 Plus other necessary pieces
Online services ATLAS control room PCs Monitoring farm 32 PCs File Servers Gateways Web servers Infrastructure all tested during many runs February 12th, 2008 TDAQ commissioning and status

16 TDAQ commissioning and status
TDAQ software Provides common tools for Control Configuration Configuration and Conditions Databases Monitoring Current version tdaq Validation via technical run 4th – 11th February Synchronized with HLT February 12th, 2008 TDAQ commissioning and status

17 Monitoring and Data Quality
Extensive framework already exists Many older and more mature tools Status displays, histogram producers, gatherers, displays, data quality Newer tools are also available and being improved/extended Monitoring Data Archive (MDA) Histograms, information automatically stored in CASTOR Operational Monitoring Display (OMD) Configurable display of any published information Time evolution, statistical analysis Trigger Presenter (TriP) Signal point of display of Trigger quantities at all levels Remote online monitoring becoming a reality: Web Monitoring Interface has been commissioned Run Status: Data Quality: Online remote access to P1 during data taking is being assessed See February 12th, 2008 TDAQ commissioning and status

18 TDAQ commissioning and status
Trigger Presenter February 12th, 2008 TDAQ commissioning and status

19 Technical Run 4th-11th Feb
Concentration on stress tests Stress data flow at all levels Heavy use of new Run Control implementation Achievements Stable running (several hours without intervention) Event sizes from 1 MB to 10 MB Event Building and Data Writing ran at Gbit link limits Controlled ~1500 applications over 350 nodes Successful, though some tweaks needed in error handling Playback of M4, M5 and Monte Carlo data to test all algorithm slices Feedback of problems useful for M6 preparation Generated 1031 data set used to test HLT menu for initial running February 12th, 2008 TDAQ commissioning and status

20 TDAQ commissioning and status
Technical Run Display 1.5 hour running time stable trigger rate memory leak spotted February 12th, 2008 TDAQ commissioning and status

21 TDAQ commissioning and status
Summary Vast majority of hardware now installed And tested in many detector and technical runs Most of requirements for initial luminosity met Large program of HLT node installation planned Commissioning weeks progressively more successful Mx weeks: More detectors, more stability Technical runs more ambitious Work to do Ongoing software development, improvement and testing Timing of Level-1 trigger system More experience with realistic triggers, rates, at all trigger levels Learn how to operate in 24/7 mode February 12th, 2008 TDAQ commissioning and status


Download ppt "TDAQ commissioning and status Stephen Hillier, on behalf of TDAQ"

Similar presentations


Ads by Google