Presentation is loading. Please wait.

Presentation is loading. Please wait.

Technical Foundations & Enabling Technologies – DS4

Similar presentations


Presentation on theme: "Technical Foundations & Enabling Technologies – DS4"— Presentation transcript:

1 Technical Foundations & Enabling Technologies – DS4
Andrew Faulkner

2 Technical foundations Enabling Technologies
Remit: Technical foundations and Enabling Technologies The Demonstrator is: 2-PAD 4 December 2018 SKADS Workshop 2006

3 Overall There are 3 more years......
DS4 very broad range with many institutions involved Schedule is disrupted – particularly in UK – due to funding delays (funds now awarded) We will deliver by June 2009 There are 3 more years...... 4 December 2018 SKADS Workshop 2006

4 DS4 work schedule 2006 Investigate and consider any possible approach.
Blue Sky etc... 2007-Q1 Select 2 or 3 of the most likely approaches 2007 Prototyping and developing phase. Build models, bring together systems 2008-Q1 Select 2-PAD components and finalise 2-PAD design note: individual subsystem work will continue 2008 Build 2-PAD 2009-1H Test 2-PAD and write report Report on advances in subsystem research 4 December 2018 SKADS Workshop 2006

5 Risks Low Risk: the components exist, but can be improved....
Antenna array, needs performance and cost and ease improvement LNA, the system noise and the cost need to be improved Processing, currently far to little capacity, but will work at some limited bandwidth High Risk: does not exist... Low power, low cost high speed ADC Cheap enough analog links – must be <€5 each RFI mitigation - unproven 4 December 2018 SKADS Workshop 2006

6 We need information from Site surveys
Bits Digitisation is not to do with instrument dynamic range! It is to do with the RFI environment. To make a practical all-digital aperture array must use minimal digitisation e.g. 4-bits CANNOT design for a European environment!! We need information from Site surveys First cut suggests that 4-bits is OK...(phew!) 4 December 2018 SKADS Workshop 2006

7 2-PAD System Consider Station level AA with 2-PAD as a subsystem
Hence understand scaling and processing issues Distances, cooling, power etc Station wide construction requirements Reliability analysis (system layout vital) Important to have benchmark specification! Building first model Focus on the bottlenecks Possibility/availability of components Cost 4 December 2018 SKADS Workshop 2006

8 Possible Station - Side view
4 December 2018 SKADS Workshop 2006

9 Possible Station - Side view
Element array 50m x 50m Inflatable Ray dome Short range analogue links from elements to local processing Array physical support grid To scale Entrance Inflation pump Station Proc. Local P. Desert FOV processing + ¼ tile processing 10m x 5m x 2.5m FOV processing + ¼ tile processing 10m x 5m Array supports providing ~1.6m headroom Cooling system Using heat transfer ground Optical fibre digital links Tile processing for ¼ of array 5m x 5m x 2.5m 4 December 2018 SKADS Workshop 2006

10 Station Layout (looking up) 4 December 2018 SKADS Workshop 2006
Short range analogue links from elements to local proc (only ¼ shown) Matrix of supports ~2m spacing (625) Local Proc. Local Proc. Inflatable Ray dome Station Layout (looking up) Element array 50m x 50m Optical fibre digital links Entrance Station Processing Local Proc. Wide area fibre link to Correlator Tile processing for ¼ of array 5m x 5m Inflation pump FOV processing + ¼ tile processing 10m x 5m 4 December 2018 SKADS Workshop 2006

11 Tile Receiving elements
Vert. Pol. Horiz. Pol. Antenna LNA Filter + Differential Line driver +ve Reg Reg Individual PCB Processing centre Low cost screened twisted pair 20m max 4 December 2018 SKADS Workshop 2006

12 ‘Tile’ configuration … … … … … … … … … … … … … … … … … … … … … … … …
1 2 3 4 5 6 7 12 13 14 15 element receiver = Notes: 16 elements / side Groups of 16 Rx in a cluster (4x4) Overall size: 3.0m square 9.0m2 512 links / tile (2x16x16) 4x4 receiver units Analogue twisted pair to Processing Centre 4 December 2018 SKADS Workshop 2006

13 Overall Station } .. .. To Correlator ….. ….. ….. ….. .. . Bunkers
Assumes 4-bit samples 256 Tile processors 8 (say) FOV processors 1GHz signals From each element 600MHz BW FOVs; 8 per tile 256 beams of 600MHz BW per FOV 16 x 16 array of Tiles ~2300 m2 Bunkers TP1 FOV1 TP2 .. } TP3 . TP17 FOV2 .. TP18 TP19 To Correlator ….. ….. ….. ….. FOV8 .. TP254 TP255 256 x 8 5-10Gb Optical fibres 32 off 40Gb Optical fibres per FOV polarisation TP256 256 x 256 1GHz Analog links 4 December 2018 SKADS Workshop 2006

14 possible, practical and cost effective
Final Thoughts.... Cost dominated by array and analogue links Total power requirements vital Power and cost of ADC an issue Communications for the internal data streams Continue system design: Frequency dependant aperture Calibration approaches Independent many small beams over whole scan angle Flexibility on beams/bandwidth/sampling for Tx to correlator On SKA timescales: a digital AA appears: possible, practical and cost effective 4 December 2018 SKADS Workshop 2006


Download ppt "Technical Foundations & Enabling Technologies – DS4"

Similar presentations


Ads by Google