1 MAMM Site Review Acquisition Plan

2 MAMM Acquisition Goals
Cover high priority areas with F1 beam. Complete Ascending and Descending coverage. Minimize use of onboard recorder maximize real-time link to McMurdo GRS. 3 identical cycles to obtain interferometric coverage.

3 High Priority F1 Target Areas

4 SAR, OBR & Station Usage Total SAR on-time: 1506.5 min.
RTM: min OBR: 596.0 Total Number of Data Acquisitions: 818 RTM: 532 OBR: 286 Fairbanks: Gatineau: Prince Albert:

5

6

7 Mission Results Cycle-1: 824 scheduled Cycle-2: 829 scheduled
782 acquired 42 lost Cycle-2: 829 scheduled 773 acquired 56 lost Cycle-3: 830 scheduled 817 acquired 13 lost

8 Cycle-1 Ascending Cycle-1 Descending

9 Cycle-2 Ascending Cycle-2 Descending

10 Cycle-3 Ascending Cycle-3 Descending

11 Cumulative Ascending

12 Cumulative Descending