Lehigh Canal Spoil Removal At Old King’s Road
2
Lehigh Canal Spoil Island Location
3
The spoil is a result of the erosion from the Lehigh canal construction and 2 weir failures
4
S.E. Cline had the best method at the best price of $98,325.
A request for proposal was advertised that asked for a qualifications, a proposed method and a bid price. S.E. Cline had the best method at the best price of $98,325.
5
2016 Proposed Budget Budgeted $110,000 S.E. Cline Contract $98,325
6
Tentative Schedule Construction window
October 1, 2015 – January 1, 2016