Download presentation
Presentation is loading. Please wait.
Published bySusanti Tanuwidjaja Modified over 6 years ago
1
Lecture 6 scrapers TSP-308 MPK Ferdinand Fassa
2
OUTLINE Introduction Types of Scrapers Scraper Production Chart
3
INTRODUCTION Excavating, loading, hauling, & dumping over medium distances. Can be used with pusher tractor for increased production. Some models have self loading capabilities Economical over a wide range of haul lengths Can self load and not dependent on other equipment Scraper are available with loose heaped capacities up to about 44 cy
4
Types of Scrapers Push-Loaded: Single Powered Axle
6
Types of Scrapers Push-Pull: Tandem- Powered Axle
7
Types of Scrapers Auger Scraper
Can self-load in difficult condition (frozen material, lime-stone) More costly to own and operate than conventional single-or tandem machine
8
Types of Scrapers Elevating is loading and hauling scraper
Used for utility work Very good in small quantity situation No pusher required
10
Scraper Production Chart
11
Average Speed Factors When machinery are required to accelerate and stop in the same section, apply the squared value from column one.
12
Scraper Fixed Time, min
13
Scraper Production Example
Problem Estimate the production of a single two-axle scraper Travel time curves are shown on Figures below, Fig. 4-4 & 4-5. Max Heaped Volume = 31 LCY Max Payload = 75,000 lb Material: Sandy Clay, 3200 lb/BCY, 2650 lb/LCY, Rolling Resistance = 100 lb/ton, Operating Conditions = Average
16
Scraper Production Example
Haul Route: Section 1. Level Loading Area Section 2. Down a 4% grade, 2000 ft Section 3. Level Dumping Area Section 4. Up a 4% grade, 2000 ft Section 5. Level Turnaround, 600 ft Turnaround Load Area 4% grade Dump Area
17
Scraper Production Example
Loads per Cycle Heaped Cap. Wt. = 31.0 LCY x 2,650 lb/LCY = 82,150 lbs 82,150 lbs exceeds the 75,000 lbs Rated Max Payload of the Scraper. The maximum scraper volume is limited by weight to = 75,000 lbs (Rated Wt)/ 3,200 lb/BCY = 23.4 BCY/Load
18
Scraper Production Example
19
Scraper Production Example
Travel Time: Section 2 ~ Down a 4% Grade, 2,000 ft. (1% Eff.) TT2=1.02 min (Figure 4-4) Section 4 ~ Up a 4% Grade, 2,000 ft. (9% Eff.) TT4=1.60 min (Figure 4-5) Section 5 ~ Level Turnaround, 600 ft. (5% Eff.) TT5=0.45 min (Figure 4-5) TT= = 0.45 = 3.07 min
21
Scraper Production Example
Travel Time: Section 2 ~ Down a 4% Grade, 2,000 ft. (1% Eff.) TT2=1.02 min (Figure 4-4) Section 4 ~ Up a 4% Grade, 2,000 ft. (9% Eff.) TT4=1.60 min (Figure 4-5) Section 5 ~ Level Turnaround, 600 ft. (5% Eff.) TT5=0.45 min (Figure 4-5) TT= = 3.07 min
23
Scraper Production Example
Travel Time: Section 2 ~ Down a 4% Grade, 2,000 ft. TT2=1.02 min (Figure 4-4) Section 4 ~ Up a 4% Grade, 2,000 ft. TT4=1.60 min (Figure 4-5) Section 5 ~ Level Turnaround, 600 ft. TT5=0.45 min (Figure 4-5) TT= = 0.45 = 3.07 min
24
Scraper Production Example
Fixed Cycle (Table 4-7) – Average Conditions – Single Engine Spot = 0.3 min. Load = 0.6 min. Maneuver & Dump = 0.7 min. Total Fixed Time = = 1.6 min Total Cycle Time = = 4.67 min. Estimate Production = 23.4BCY/Load x [(50min/h)/(4.67min/Load)] = 251 BCY/h
25
Scraper Fixed Time, min
26
Scraper Production Example
Fixed Cycle (Table 4-7) Load Spot = 0.3 min. Load = 0.6 min. Maneuver & Dump = 0.7 min. Total Fixed Time = = 1.6 min Total Cycle Time = = 4.67 min. Estimate Production = 23.4BCY/Load x [(50min/h)/(4.67min/Load)] = 251 BCY/h
27
Push-Loading
30
Typical Pusher Cycle Time, min
31
Number of Scrapers Served, Pushers Required & Production
(# of scrapers that can be handled by one pusher w/o scraper delay) (# of pushers required to service a fleet of scrapers: round up to next integer)
32
Scraper Push-Loading Example
Problem The estimated cycle time for a wheeled scraper is 6.5 min. Calculate the number of pushers required to serve a fleet of nine scrapers using pushers. Determine the result for both backtrack and chain loading methods.
33
Scraper Push-Loading Example
Cycle Times from Table 4-8
34
Optimal Load Time
35
Optimum Load Time
36
Cycle Time minus Load Time = 3.0 min.
37
CONSTRUCTION EQUIPMENT AND METHODS
Next Week: Lecture 7 CONSTRUCTION EQUIPMENT AND METHODS
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.