Download presentation
Presentation is loading. Please wait.
1
2K Cold Box Cost, Schedule & FDR Summary
Mike Bevins LCLS-II 2 K Cold Box FDR March 9, 2017
2
Schedule Overview 2K Cold Box Delivery Milestones
2K Cold Box FDR, Mar 9, 2017
3
2K Cold Box Cost Est & Procurement Approach
Cold Compressors CP1 + CP2 (6 stages per plant) - ~$5M FDR completed in Jan 2017, Fabrication underway 2K Cold Box Vendor Fabrication CP1 + CP2 - ~$6.6M Best value solicitation Material to be provided to Cold Box Vendor: Long lead items (cryo valves/flowmeters) procured by JLab in parallel with 2K CB solicitation Bayonets (fabricated at JLab) CC Casings (AirLiquide) 2K Cold Box FDR, Mar 9, 2017
4
Procurement/Fabrication/Commissioning Schedule
Cold Compressors Award Cold Compressors 23-Aug-16 Cold Compressor Final Design Review 17-Jan-17 CP1 CC Casings Fabrication Complete 17-Jul-17 CP2 CC Casings Fabrication Complete 16-Mar-18 2K Cold Box Finialize Procurement Package (Drawings & Spec) 10-Apr-17 Release 2K Cold Box RFP 11-Apr-17 Award 2K Cold Box 27-Jul-17 Fabricate CP1 2K Cold Box 28-Jul Mar-18 Receive CP1 2K Cold Box at SLAC 29-Mar-18 CP1 2K Cold Box Commissioning 1-Nov Feb-19 Receive CP2 2K Cold Box at SLAC 8-Mar-19 CP2 2K Cold Box Commissioning 26-Jun Jul-19 2K Cold Box FDR, Mar 9, 2017
5
The 2K Cold Box design maturity is commensurate with FDR
2K CB FDR Summary The 2K Cold Box design maturity is commensurate with FDR Process design 3D model/drawings Stress Analysis Procurement specification The design is sufficiently mature to release the RFP on schedule 2K Cold Box FDR, Mar 9, 2017
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.