BACKGROUND OF THE STATION CHALLENGES TECHNICAL SOLUTION BY KENGEN FINANCIAL IMPLICATIONS RECOMMENDATIONS

3 INTRODUCTION GITARU POWER STATION
Gitaru is the 3rd Hydro Power Station in the Lower Tana cascade comprised of three hydro generating units with a total capacity of 225MW- Largest Hydro Plant. Unit 2 and Unit 3 were installed and commissioned between 1975 – 1978 each generating 72.5 MW Unit 1 was installed and commissioned in 1999 and has a generating capacity of 80MW through EPC contracting.

4 INTRODUCTION SYNOPSIS Gitaru Unit 1 was running on SIEMENS S5 PLC -
18yrs+ of service The machine has no Manual Control Panel At the onset of SCADA phase 1, another PLC was incorporated to interface the S5 PLC to the control HMI system

5 GITARU UNIT 1 PLC ARCHITECTURE
INTRODUCTION GITARU UNIT 1 PLC ARCHITECTURE S5 PLC I/O CARDS MOMENTUM PLC HMI HMI – Human Machine Interface PLC – Programmable Logic Controller

6 GITARU UNIT 1 PLC ARCHITECTURE
INTRODUCTION GITARU UNIT 1 PLC ARCHITECTURE S5 Siemens PLC Input/Output Cards

7 INTRODUCTION PLC and EchoLink Interfaces HMI

8 HISTORY PROJECT: SCADA PHASE I
KenGen team involved with tender preparation to determine scope of works and evaluation Contract was awarded to Iberdrola Company, Spain Design review and approvals Theory and Practical training conducted at contractor factory. On site skill/knowledge transfer during/after project execution- use of tools, troubleshooting and system maintenance.

9 HISTORY SCADA HISTORY SCADA PHASE I : Implementation 2006 - 2010
CONTRACTOR: IBERDROLA Co., SPAIN CONSULTANT: ENG. ELUID WAMAKIMA KENGEN TRAINED STAFF : 5 TOOLS : Concept - PLC Program, PcVue - Human Machine Interface (HMI) HARDWARE :Schneider series, Modicon Quantum I/O cards

10 GITARU UNIT 1 PLC UPGRADE
GITARU U1 PROJECT GITARU UNIT 1 PLC UPGRADE WHY????

11 BACKGROUND Hardware Challenges No support from the manufacturer
Black box - No familiarity to the installed system by the T/S team Outdated cards and technology Tools to interrogate the system outdated - PG Programma laptop the size of a modern day travel bag

12 BACKGROUND Operational Challenges
Too many points of failure – many interfaces used in the control system – Momentum PLC, EchoLink Some failures required PLC program restoration Intermittent unexplained machine trips - Not captured in events This resulted in:- Customer reservation/lack of confidence on machine reliability and availability Loss of revenue to the company

13 BACKGROUND A numerical relay introduced to isolate and identify group trips Relay Installed

14 LOSS OF REVENUE DUE TO THE FREQUENT TRIPS

15 BACKGROUND Recent breakdown
25th May 2017, machine out for 46hrs – DC failure, loss of interface PLC program, restored with 1 active PLC Translates = KES 930,000,000.00 Standby PLC failure – Error status CPU battery spares unavailable

16 WAY FORWARD…

17 TECHNICAL SOLUTION BY KENGEN
KenGen Technical Services team floated a proposal 2014;- To change existing control system to a modern compact PLC that can be directly interfaced to SCADA system Automation, interface works to be carried out by KenGen Control and SCADA Engineers Proposal approved by management Single source (Direct procurement) of the equipment and tools granted

18 TECHNICAL SOLUTION BY KENGEN
Working Teams Internal capacity was built during SCADA Phase I project in 2010 T/S Engineers and ICT department support and maintain installed control systems Skills/knowledge transfer: to new staff who joined the company - post 2010

19 TECHNICAL SOLUTION BY KENGEN
PROJECT EXECUTION Procurement of equipment and tools – 2014 Pre outage works - signal list preparation 2014/2015 Delivery of equipment to site Outage requested and granted on 05th June, 2017 Teams involved: Technical Services Engineers ICT Department

20 TECHNICAL SOLUTION BY KENGEN
Roles Technical Services: Procurement: PLCs, I/O cards, interface cable, crimping tools Compilation of signal list PLC Programming - control logics Signal Functional Checks Commissioning Update drawings

21 TECHNICAL SOLUTION BY KENGEN
Internal Resources Roles ICT Department: Set up communication infrastructure HMI design DBS/OPS updates – Gitaru/ Kamburu Plant Information (PI) Configuration HMI Function checks

22 TECHNICAL SOLUTION BY KENGEN
JOH-KGN JvW-X1 TECHNICAL SOLUTION BY KENGEN Capacity Building To cater for skill/ knowledge transfer, staff from other areas were invited to participate in the project. Team constituted staff members from:- Tana Kamburu Gitaru Stima Plaza Turkwel Sondu

23 TECHNICAL SOLUTION BY KENGEN
PROJECT EXECUTION Number of days = 30 days Program the new PLC and design the HMI interface Decommission the old PLC, I/O devices Mounting of the new PLC, I/O devices Rewiring of the new devices Download of the new PLC program Dry checks of the signals Wet test and command signals Function checks Sequence checks – Spin; Excite; Synchronize Unit Declared available

24 FINANCIAL IMPLICATIONS
CASE STUDY: TANA DCS RE-ENGINEERING WORKS Tana Power Station DCS upgrade was done by Iberdrola, Spain PLC reprogramming and upgrade of the HMI system of all 4 generating units 1 unit was done by the contractor to completion Other 3 units done by KenGen Services rendered:- Engineering service Commissioning service Factory Training

25 FINANCIAL IMPLICATIONS
CASE STUDY: TANA DCS RE-ENGINEERING WORKS COSTS: Unit 1 Price Schedule *1 EURO = KES ITEM DESCRIPTION PRICE(€) 1 Engineering Services Software configuration (PLC and HMI) 57,748.86 2 Commissioning services 58,128.79 3 Employee Participation (Skills Transfer) Training at contractor factory 12,668.95 TOTAL 128,546.60

26 FINANCIAL IMPLICATIONS
JOH-KGN JvW-X1 FINANCIAL IMPLICATIONS CASE STUDY: TANA DCS RE-ENGINEERING WORKS Costs incurred DESCRIPTION NO COST (KES) 1 Administrative costs (Per Diem/Callouts 2,626,000.00 2 Engineering, Commissioning & Training Services 15,869,077.80 TOTAL 18,495,077.80

27 FINANCIAL IMPLICATIONS
JOH-KGN JvW-X1 FINANCIAL IMPLICATIONS CASE STUDY: GITARU UNIT 1 PLC UPGRADE Costs incurred DESCRIPTION COST (KES) 1 Administrative costs (Per Diem/Callout/Lunch/Mileage) 5,935,000.00 2 Training Component 1,138,208.00 TOTAL 7,073,208.00

28 FINANCIAL IMPLICATIONS
JOH-KGN JvW-X1 FINANCIAL IMPLICATIONS CASE STUDY: PROJECT COST COMPARISON GITARU U1 PLC UPGRADE TANA DCS UPGRADE DESCRIPTION COST (KES) 1 Engineering & Commissioning -Administrative costs (Per Diem/Callout/Lunch/Mileage) 5,935,000.00 Administrative costs (Per Diem/Callouts 2,626,000.00 2 Training component 1,138,208.00 Engineering, Commissioning & Training Services 15,869,077.80 TOTAL 7,073,208.00 18,495,077.80

29 RECOMMENDATIONS Design development Installation Commissioning
JOH-KGN JvW-X1 RECOMMENDATIONS 1. Project design & execution: Experienced Engineers in operations division be involved in areas of project development and execution: Design development Installation Commissioning 2. Capacity building Nominated staff who attend specialized trainings to carry out internal trainings to transfer/share knowledge.

30 RECOMMENDATIONS 3. Future Projects 4. Systems Audit
JOH-KGN JvW-X1 RECOMMENDATIONS 3. Future Projects Projects of this nature can be done in partnership with the contractor to enhance knowledge transfer. This shall boost the confidence in the system and encourage innovative practices and save on costs across the company. 4. Systems Audit Installed system to be audited over a period to check on the system performance, availability of critical spares and technological advancements

31 Teams at Work

32 Teams at Work

33 Teams at Work

34 Teams at Work

35 Old PLC Configuration

36 New PLC Configuration PLC Rack Terminal blocks Input/ output cards

37 Operations Director and Area Manager Addressing the Team

38 VOTE OF THANKS ENTIRE MANAGEMENT TEAM WORKING TEAMS

39 THANK YOU


Download ppt "GITARU UNIT 1 PLC UPGRADE"

Similar presentations


Ads by Google