Download presentation
Presentation is loading. Please wait.
1
SENIOR DESIGN PROJECT P08455
Value Engineering in a Manufacturing Facility Compressor Stand for Final Assembly SENIOR DESIGN PROJECT P08455
2
The Team John Foley (ME), Eric Hodecker (ME), Chris Bulawa (ME),
and John Roylance (IE) and Stephen Papa (IE- Project Manager)
3
Current Process Head Pipe Clamps to Support Head Top Half is Removed
During Final Assembly Bundle Cradles Complete Bundle on Contract Tooling 3
4
Value Engineering in a Manufacturing Facility
Objective: Design and build a safe compressor final internal assembly stand for the Olean Manufacturing Facility. Iteration 1 - Key Needs: Adjust to different sized compressors. [Length (35”-86”) and Diameter 21”- 43”)] Be able to support up to 30,000lbs for a week. Support different sized Heads Work bench to support assembly tools [12” x 18” and support 100lbs.]
5
Final Design - Iteration 1
Removable and adjustable tool table Adjustable plates for different diameter compressors Track allows for adjustment to different length compressors
6
Pin adjusted height with 180o lateral motion
Tool Table - Iteration 1 Pin adjusted height with 180o lateral motion Non-slip tool tray Detachable base
7
Compressor Stand for Final Assembly – Key Needs Iteration 2:
The original budget was cut down to $5,000 between Senior Design I, and Senior Design II. After crucial evaluation of the current project, the team decided to eliminate some of the secondary needs without compromising the primary needs in an effort to meet the new budget. Key Needs Iteration 2: Adjust to different sized compressors. [Length (35”-86”) and Diameter 21”- 43”)] Be able to support up to 30,000lbs for a week
8
Final Design - Iteration 2
9
Test Plan Testing begins when fabrication of the stand is completed (5/9) Testing will consist of: Load tests (to be preformed by Dresser-Rand) Ergonomic tests Approval by Dresser-Rand management and operators Testing will be performed at the Dresser-Rand Olean facility Senior Design Team and Dresser-Rand Stakeholders will be present for testing.
10
System Test Results - Ergonomic Tests
3DSSPP Stress Analysis software was used to test biomechanical stresses placed on a stand operator. Fig. 1” shows the body position used to test the biomechanical stress on the operator. “Fig. 2” shows the percent of males able to handle the stress at each joint. These percentiles fall within the acceptable limit of 90 percent of males. Work Instructions were presented and accepted by Dresser-Rand Figure. 1 Figure. 2
11
System Test Results - Approval by Dresser-Rand management and operators:
Overall the design was robust and well thought out The group was eager for feedback from our assemblers. With only minor adjustments, the bundle stand can be used for production assembly The group was able to explain the different functions/ applications of each component clearly and effectively Developed comprehensive work instructions for alignment, use, and handling of the bundle stand
12
MSD II Project Schedule Milestones
Ergonomic Evaluation and Training Test Field Demo Functional / Performance Review Poster Submitted Final User Documentation and Final Presentation Senior Design 2 Starts Working on Test Plan Develop Work Instructions Work with PE to Certify the Design Work with the Manufacturer Order Parts Manufacturing Transportation
13
Conclusion Approval by Dresser-Rand management and operators
The stand prototypes were delivered to the Dresser- Rand Olean facility on May 9th, 2008. It was determined that the stand we produced would provide an excellent basis for the future stands to be used in Dresser-Rand manufacturing facilities worldwide. Project was under Budget
14
Acknowledgements – THANK YOU!
Dresser- Rand Mark Wilson Michael Bunce RIT Dr. Taylor Dr. Debartolo Dr. Kaemmerlen John Bonzo Justin Stabb (Certified Professional Welder) RIT Machine Shop
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.