FACILITIES, PLANNING, AND CONSTRUCTION
JANUARY 30, 2014 CONSTRUCTION REPORT
2
Facilities under Construction: Facilities in Planning/Bidding Stage:
Area Currently Under Construction/ Planning Facilities under Construction: V.R. Eaton High School ,000 SF __________ Total ,000 SF Facilities in Planning/Bidding Stage: Peterson E.S. Addition ,000 SF Beck E.S. Addition ,000 SF ____________ Total ,000 SF Total Projects under Construction, Planning and Bidding: 562,000 SF
3
V. R. Eaton High School Status: Pier drilling is complete
Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start Date: Spring 2013 Completion Date: August 2015 Status: Pier drilling is complete Geothermal wells are being drilled Grade beams are 45% complete Foundation pours are underway Rough electrical and plumbing is being installed Site grading and utility installation is underway Steel erection will begin in March
4
May 2013 January 2014
7
Peterson Elementary School Addition
Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Design Complete GMP submitted for School Board approval Construction begin in February
8
Beck Elementary School Addition
Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Design Complete GMP will be submitted for School Board approval in February Construction begin in March
9
SECO Energy Grant OLC- Wind Turbine and Solar Array Operational
Central Campus- Wind Turbine and Solar Array Operational
12
FACILITIES, PLANNING, AND CONSTRUCTION
JANUARY 30, 2014 CONSTRUCTION REPORT