Industrial Electrical Engineering and Automation
Blackout in Italy Sture Lindahl Industrial Electrical Engineering and Automation
2
Introduction Blackout on 2003-09-28 at 03:28 Affected all Italy except
New world record 58 million persons No expansion of nuclear power according to referendum Yearly electric energy import: 17% Power import: MW Sture Lindahl, LTH/IEA
3
Background Italy lost all transmission lines from France, Switzerland, Austria and Slovenia The blame game started RTE has requested UCTE to carry out a disturbance investigation UCTE will report on Sture Lindahl, LTH/IEA
4
First Event At 03:01, sustained outage of the 400 kV Metten – Lavorgo (in Switzerland) At 03:15, ETRANS called GRTN and requested a reduction of the physical power flow to Italy The import was reduced by 200 MW down to the agreed MW Sture Lindahl, LTH/IEA
5
Fax Information from Switzerland
Sture Lindahl, LTH/IEA
6
Second Event At 03:25 the 400 kV Sils-Soasa (in Switzerland) tripped and the reason has not been published Sture Lindahl, LTH/IEA
7
Fax Information from Switzerland
Sture Lindahl, LTH/IEA
8
Affected Region Sture Lindahl, LTH/IEA
9
Restoration At 03:45, restoration co-operation started
At 13:00, the transmission lines to Italy were restored At that time Italy imported about 85% of the value planned before the blackout At 15:45, significant parts of Italy was not supplied At 20:00 most of the load was restored Sture Lindahl, LTH/IEA