1 IHEP Cryomodule Status
Jiyuan Zhai On behalf of the IHEP ILC SRF R&D Team AWLC14, May 14, Fermilab

2 Outline IHEP ILC-TC1 Cryomodule Assembly Horizontal Test Facilities
Cavity Fabrication

3 IHEP ILC-TC1 Cryomodule
Short cryomodule with one low- loss large grain 9-cell cavity (VT 20MV/m, Q0=1.4E10) Cylindrical magnetic shield inside helium vessel STF type input coupler and tuner Module assembly to complete in July 2014, horizontal test in 2015

4 Cryomodule Assembly Assembly Hall in IHEP Building #2

5 Cavity Clean Room Assembly

6 Cavity Clean Room Assembly
Beam Tube Assembly Gate Valve Assembly Cavity Assembly Prep Careful Clean Room Assembly Operations (PFFA)

7 Cavity Clean Room Assembly
Slow Pumping and N2 Purging 2mm Middle-position slide jack tuner with four guiding rods Helium vessel bellow and tuner flanges sagging when loose the support fixtures; will be restored when the tuner is installed. Coupler Mounting Test

8 Outline IHEP ILC-TC1 Cryomodule Assembly Horizontal Test Facilities
Cavity Fabrication

9 Horizontal Test Facility Layout
IHEP Building #1 Cryogenic Plant In commissioning Power Source Deliver in end 2014 Tunnel Horizontal test & beam test Vertical test Dewar Deliver in September

10 Cryogenic System in Commissioning
Cold box and compressor: refrigeration liquefication: 284 L/h 2K pumps: Pa

11 1.3 GHz Klystron and Modulator Ordered
1.3 GHz 5 MW Klystron and Marx Modulator will deliver in end 2014

12 Outline IHEP ILC-TC1 Cryomodule Assembly Horizontal Test Facilities
Cavity Fabrication

13 TESLA-like Cavity Fabrication
End groups EBW ongoing Cavity EBW to be done in July Process and test at KEK

14 TESLA Cavity Production
HERT Company FG TESLA 9-cell cavity Pressing and EBW test and optimization One prototype in 2014

15 Summary IHEP ILC test cryomodule assembly is ongoing and will be finished in July 2014. Hardware preparation, environment and component cleanliness, vacuum, alignment and assembly procedures are studied and conducted carefully for cavity clean room assembly. Cryogenic system and power source will be ready in end for the module horizontal test. Prototype production of a fine grain TESLA-like 9-cell cavity and a fine grain TESLA 9-cell cavity will be done in mid and end respectively.

16 Thank you!