1 Construction and First Coo-down Test of cERL Injector Cryomodule
E. Kako, Y. Kondo, S. Noguchi, T. Shishido, Y. Yamamoto, K. Watanabe (KEK, SC-Cavity Gr.) K. Hara, T. Honma, Y. Kojima, H. Nakai, K. Nakanishi (KEK, Cryogenic Gr.) H. Hitomi, K. Sennyu (MHI, Mihara) Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

2 OUTLINE Design Feature of cERL Injector Cryomodule Cryomodule Assembly
First Cool-down Test : (Low RF power measurements) 4. Summary Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

3 OUTLINE Design Feature of cERL Injector Cryomodule Cryomodule Assembly
First Cool-down Test : (Low RF power measurements) 4. Summary Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

4 Injector Cryomodule for cERL (1)
Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

5 Injector Cryomodule for cERL (2)
Ibeam = 100 mA, Ebeam = 10 MeV for 3GeV-ERL Required RF input power = CW 180 kW / coupler Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

6 OUTLINE Design Feature of cERL Injector Cryomodule Cryomodule Assembly
First Cool-down Test : (Low RF power measurements) 4. Summary Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

7 Assembly of Injector Cryomodule (1)
April 25th, 2012 Exchange of RF feedthroughs Cavity string assembly in clean room Attachment of input couplers Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

8 Alignment of three cavities
Assembly of Injector Cryomodule (2) Alignment of three cavities Assembly of slide-jack tuner system Assembly of 2K-He line Installation of 5K-He panels Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

9 Assembly of Injector Cryomodule (3)
Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

10 OUTLINE First Cool-down Test ; (Low RF power measurements)
a. Cool-down procedure b. Temperature distribution at 2K c. Heat load measurement d. Frequency change e. Slide-jack tuner performance f. Piezo tuner performance g. Input-phase adjustment Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

11 History of cool-down (1)
Sept. 11 (Tue) 17:00 Measurement at 300 K Sept. 12 (Wed) 10:00 Cool-down / start 19: K Cool-down / stop Sept. 13 (Thu) 8: K / start 17: K / stop Sept. 14 (Fri) 8: K / start 17: K / stop Sept. 15 (Sat) --- --- Sept. 16 (Sun) --- --- Sept. 17 (Mon) --- --- Sept. 18 (Tue) 8: K / start 18: K / stop Sept. 19 (Wed) 8: K / start 19: K / stop Sept. 20 (Thu) 8: K / start 16: K ; Measurement at 4.2 K 18:00 / stop Sept. 21 (Fri) 8: K / start 13: K 16: K ; Measurement at 2.0 K 17:00 / stop 20: K Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

12 History of cool-down (2)
Sept. 23 (Sun) 10: K 15: K Sept. 24 (Mon) 8: K Cool-down / start 17: K 18: K ; Low RF power tests at 2K 24:00 Cool-down / stop Sept. 25 (Tue) 8: K / start 10: K 12: K ; Low RF power tests :00 / stop Sept. 26 (Wed) 8:00 / start 12: K ; Low RF power tests :00 / stop Sept. 27 (Thu) 8:00 / start 11: K ; Low RF power tests :00 / stop Sept. 28 (Fri) 8:00 / start 11: K ; Low RF power tests :00 / stop Sept. 29 (Sat) 9: K natural warm-up without heater Oct. 01 (Mon) 8: K Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

13 Temperature Distribution at 2K (1)
Temperature sensors : Cernox = 48 Pt-Co = 12 CC = 36 2.89 K 89.8 K 4.2K-He reservoir panel for input thermal anchors 68.9 K 5.15 K 3.54 K 3.71 K 5.25 K 70.0 K 90.5 K Temperature at Input Couplers (without dynamic loss) Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

14 Temperature Distribution at 2K (2)
HOM-cup HOM -connector Thermal anchor to 2K ave. temp. at 15 HOM couplers ; HOM-cup = 4.16 K, (3.24~6.27 K) HOM-connector = 6.82 K, (5.69 ~ 9.23 K) Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

15 Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

16 Heat Load Measurement (Preliminary)
Static heat load ; 2K Static heat load ; 4.2K ave. 2K heat load = 12 W (including 2K cold-box = 1 W) Cryomodule = 11 W at 2K Estimation = 14 W, including 1 W/coupler (x6), 0.2 W/HOM-cable (x15) and others. ave. 4.2K heat load = 48 W (including 2K heat load = 12 W) Cryomodule = 36 W at 4.2K Estimation = 33 W, including 3 W/coupler (x6) & 1 W/HOM-cable (x15). Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

17 Frequency change during cool-down
Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

18 Frequency change, QL at 2K
No.1 Cavity No.2 Cavity No.3 Cavity T = 300 K MHz MHz MHz T = 4.2 K MHz MHz MHz T = 2.0 K MHz MHz MHz Df = 300K/4.2K MHz MHz MHz Df = 4.2K/2.0K - 125 kHz - 150 kHz - 141 kHz Measured QL 1.41 x106 6.23 x105 6.22 x105 (Designed QL) ( 5 x105 ) ( 2 x105 ) ( 2 x105 ) Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

19 Tuner Stroke of #1, #2, #3 Cavity
at 2 K fo = MHz D fo = 1.0 MHz/mm Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

20 D f = 2. kHz Piezo Stroke of #1, #2, #3 Cavity
Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

21 Measurement of Input Phase vs Pt
3dB div. RF source Pt f f =0 f =0 f = -p f = +p f = -p f = +p Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

22 Schedule for Next Step Oct. 22 ~ Processing of Input couplers at RT (#1-Cavity) 5Hz, 10ms, 30ms, 100ms, 0.5ms, 2ms, 10ms; 60 kW 2Hz, 50ms; 1Hz, 200ms; 60 kW/coupler CW, 16 kW/coupler ; finished. (for 20 hours) Nov. 12 ~ Processing of Input couplers at RT (#2-Cavity) Dec. 03 ~ Processing of Input couplers at RT (#3-Cavity) 2013’ Jan. 08 ~ 2nd cool-down for high RF power tests Jan. 21 ~ Low power tests (with WG-system) Jan. 28 ~ High power tests (#1-Cavity, #2-Cavity) Feb. 04 ~ High power tests (#3-Cavity, #2&#3-Cavity) Feb. 09 ~ warm-up Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

23 SUMMARY Construction of injector cryomodule for cERL was completed, and the cryomodule was successfully cooled down at 2 K. Low RF power tests at 2 K were carried out, and reasonable heat loads and good tuner performance were confirmed. High RF power test is scheduled in Jan.-Feb., 2013’. Eiji Kako (KEK) 2012, Nov. 07 TTC meeting at JLab

24 Thank you for your attention.