2018 2018 Today 0% Jan 27 - Jan 31 0% 0% Feb 3 - Feb 10 Feb 7 - Feb 14
PC Image Analysis 3 days Jan 27 - Jan 31 0% PC Image Preparation 5 days 0% Feb 3 - Feb 10 Smartphone Image Preparation 6 days Feb 7 - Feb 14 0% Optimization 3 days 0% Feb 17 - Feb 21 PC Image Test 5 days 0% Feb 21 - Feb 27 Smartphone Test 5 days Feb 21 - Feb 27 0% PC Image Sign-Off 7 days Feb 26 - Mar 6 0% Smartphone Image Sign-Off 6 days Feb 28 - Mar 7 0% Documentation 3 days 0% Mar 4 - Mar 7 Helpdesk Training 1 day Mar 10 - Mar 12 Production Mar 17 2018 Day 1 6 11 16 21 26 31 36 41 46 51 56 2018 Today Project Approval Jan 21 Image Rolled Out Feb 17 Image Approved Mar 4 Project Hand-Off Mar 20