Download presentation
Presentation is loading. Please wait.
Published byRoy Lambert Modified over 6 years ago
1
Colchester Interceptor System Improvements Project
Community Meeting #1 August 25, 2016 SA Project Manager: Debbie J. Maxwell, P.E., CCM Design Engineer: Michael Baker International Construction Management: Arcadis
2
Agenda Purpose of the Project Existing System Conditions
Overview of the Limits of Service Definitions Purpose and Benefits of the Project Existing System Conditions Proposed System Improvements Project Details Site Activities & Notes of Interest Anticipated Construction Schedule Contacts Q&A
3
Purpose of the Project Limits of Service 7 Service Areas
Numerous Lift Stations Miles of Gravity Sewers Miles of Force Mains Prince William Parkway Hoadly Road Belmont Lift Station Prince William Parkway Route 1 Minnieville Road Interstate 95 Dale Blvd. Featherstone Road Project Limits H.L. Mooney Water Reclamation Facility Featherstone Lift Station
4
Purpose of the Project Definitions Gravity Sewer Lines
Sewer lines constructed to allow the wastewater to flow based on a downward slope Interceptor Sewers Gravity Sewer mains which receive the flow from collector sewers and conveys the wastewater to treatment facilities Lift Station A gravity sewer sump with a pump to lift accumulated sewage to a higher elevation Force Mains A pressurized sewer line to convey wastewater from a lift station to another service level and gravity sewer
5
Purpose of the Project Purpose of the Project Benefits of the Project
Replace an existing and aged Interceptor Sewer System Increase system capacity Reduce or eliminate stormwater and groundwater from entering the system Benefits of the Project Provide environmental benefits by relief of potential surcharge conditions Maintain service reliability
6
Existing System Conditions
Belmont Lift Station Belmont Force Main Colchester Road Gravity Sewer Discharge 48” Interceptor Sewer Featherstone Lift Station
7
Existing System Conditions
Approximately 7,600 linear feet of 36” - 48” gravity interceptor sewer Approximately 1,500 linear feet of 8” and 12” gravity sewer
8
Proposed System Improvements
Install approximately 5,411 linear feet of 30” and 36” force main Replace approximately 2,132 linear feet of 48” gravity sewer with 54” gravity sewer Install approximately 1,530 linear feet of 8” and 12” gravity sewer Construct a new lift station
9
Proposed System Improvements
Belmont Lift Station Colchester Road Gravity Sewer Discharge Marumsco Acres Lake Lift Station Belmont Force Main 54” Interceptor Sewer Featherstone Lift Station
10
Proposed System Improvements
11
Proposed System Improvements Marumsco Acres Lake Lift Station
12
Proposed System Improvements Marumsco Acres Lake Lift Station
Lift Station Details The building is 14’ x 14’ Brick siding Shingled roof The Station capacity is 350 gpm Emergency diesel engine generator as back-up power Odor Control Carbon Filters Bioxide (calcium nitrate)
13
Proposed System Improvements Marumsco Acres Lake Lift Station
14
Site Activities Activities
The Contractor will determine the final sequence of construction The Lift Station is limited to a 10 month construction period Open cutting of trenches Force Mains and some gravity Trenchless installation Boring under Featherstone Road to avoid road closures Microtunnelling for a portion of the 54” gravity main Installation of new manholes Tie-in of existing systems
15
Notes of Interest Construction Notes of Interest
Notifications will be provided by the Service Authority and the Contractor for any anticipated interruptions Access will not be interrupted Emergency Services, school buses, trash, mail and other services will not be disrupted Temporary parking areas will be coordinated with land owners, the Department of Parks and Recreation, and HOAs if needed by the Contractor prior to construction Daily clean-up by the Contractor is required A Service Authority Inspector will cover this project and others close by and will be on site on a daily basis A Construction Manager / SA Project Representative will be onsite fulltime for the duration of the project
16
Final Layout Summary Benefits Redirect flows to Belmont Lift Station
Construct a new Lift Station Extend the force main Enlarge the gravity sewer size Benefits Increase system capacity Environmental benefits Relief of potential surcharge conditions Reduce or eliminate Inflow Improve system reliability Colchester Road Gravity Sewer Discharge Marumsco Acres Lake Lift Station Belmont Force Main 54” Interceptor Sewer Featherstone Lift Station
17
Anticipated Construction Schedule
Project Duration 660 days / 21 months Project Advertisement August 2016 – November 2016 Anticipated Start Date: Award Contract in January 2017 Begin Construction in February 2017 Anticipated End Date: December 2018 Weekday Hours of Operations 7:00 a.m. to 5:00 p.m. Previously negotiated and approved night time hours Certain business parcels
18
Contacts Community Relations & Outreach Liaison Marlo Thomas Watson
Or Website: Project Specific Website:
19
Q & A Any Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.