1 Finishing Projects Fast
James R. Burns Professor of Operations Management and Information Technology Texas Tech University

2 Presentation by James R. Burns
Outline--Sources Generalities Goldratt concepts Mascitelli concepts McCONNELL concepts Kerzner concepts Maturity concepts Other sources Tuesday, March 23, 2013 Presentation by James R. Burns

3 Presentation by James R. Burns
Goal: Make some suggestions as to how projects can be completed fast and frugally Tuesday, March 23, 2013 Presentation by James R. Burns

4 Presentation by James R. Burns
Most firms Recognize project management to be a core competence today Have established project management centers of excellence for training and development of project managers and project management careers Encourage its employees to propose project initiatives with simple one-page statements of work Tuesday, March 23, 2013 Presentation by James R. Burns

5 Notes on shortening project durations
(Most of this must be done in the Planning and Budgeting stage) Crashing Reducing the duration of tasks on the critical path by adding resources Fast-tracking Starting tasks sooner Checking for parallelism opportunities in the schedule Pull as much work off of the critical path as you can Be aware of critical chain issues Tuesday, March 23, 2013 Presentation by James R. Burns

6 More Tips on shortening project durations
REUSE, REUSE, REUSE Do it right the first time Eliminate non-value-added work activities Make projects lean Avoid changes to requirements But what if the requirements are unstable?? Tuesday, March 23, 2013 Presentation by James R. Burns

7 Presentation by James R. Burns
Knowledge Reuse… Requirements Reuse Classification of projects Mapped/Programmed Projects--Everything is driven by and proceeds from the requirements Project Plan Functional Specification Design Document Code Tests and Test Documentation ALL OF WHICH CAN BE REUSED Tuesday, March 23, 2013 Presentation by James R. Burns

8 The Quality View on FAST projects:
Do it Right the First Time!!! The further down the lifecycle the defects are found, the more expensive and time consuming they are to fix. Tuesday, March 23, 2013 Presentation by James R. Burns

9 The problem of Complexity
In the early days of simpler code, it used to take a day or less to fix a bug Now, with greatly increased code complexity, it takes weeks sometimes. Complexity greatly increases time and cost Tuesday, March 23, 2013 Presentation by James R. Burns

10 Avoid changes to requirements
If possible freeze requirements during execution and control stage Tuesday, March 23, 2013 Presentation by James R. Burns

11 Lean Project Management
Customer-perceived value should drive everything What is the value proposition?? If we were to advertise in the WSJ that we have twice as many walkthroughs as our closest competition, would that garner any additional customers for us? Remove what does not add value Tuesday, March 23, 2013 Presentation by James R. Burns

12 Principles of Lean Concepts Applied to Projects
Precisely specify the value of the project Identify the value stream for each project Allow value to flow without interruptions Let the customer pull value from the project team Continuously pursue perfection Tuesday, March 23, 2013 Presentation by James R. Burns

13 Which of the following adds value?
Conducting a weekly team coordination Hunting for needed information Presenting Project status to upper management Creating formal project documents Gaining multiple approvals for a project document Waiting in queues for available resources Tuesday, March 23, 2013 Presentation by James R. Burns

14 Time Batching--Another Time Waster
Analysis paralysis Approval cycles Formal document release Regularly scheduled meetings Planning cycles Work queues Tuesday, March 23, 2013 Presentation by James R. Burns

15 More techniques for shortening projects
Scrub the requirements during or prior to the planning and budgeting stage Remove from the requirements those items that add little or no value Remember the Pareto principle—80% of the value comes from 20% of the functionality REMOVE SAFETY—GOLDRATT Resist multitasking and student syndrome Tuesday, March 23, 2013 Presentation by James R. Burns

16 Presentation by James R. Burns
Safety Extra time placed in an estimated task time Remove safety and put it in a time buffer at the end of the project Safety, when its buried in the tasks of the project, is a bad thing because of…. Multitasking, also a bad thing Student syndrome Task dependencies Can’t be passed along or accumulated Tuesday, March 23, 2013 Presentation by James R. Burns

17 Everybody overestimates the time required to do their task
According to Goldratt (This is called SAFETY, as we said) Does anybody want to talk about how much safety they put into their estimates? Is this true in software development? It is if you have an expert doing the estimating, who really knows how long it will take him Tuesday, March 23, 2013 Presentation by James R. Burns

18 What happens after that--a possible scenario
The team leader adds safety time to the task to cover his responsibilities The project leader adds more safety time The project manager may add still more safety time Tuesday, March 23, 2013 Presentation by James R. Burns

19 Implication>>>
Most of the time we have built into our projects is ….. Tuesday, March 23, 2013 Presentation by James R. Burns

20 The project manager must stay focused
Or the project will not be finished on time, within budget This means applying the Pareto principle 80% of the benefit comes from 20% of the activities By the time progress reports indicate something is wrong, its usually too late Progress reports tell you that 90% of the project is finished in 90% of the required time. However, another equal period of time is required to complete the remaining “10%,” in many cases Tuesday, March 23, 2013 Presentation by James R. Burns

21 It is hard to stay focused when:
There are too many project paths on-going, in parallel There are many critical or near critical paths There are many projects being managed concurrently Tuesday, March 23, 2013 Presentation by James R. Burns

22 Measurements are a major problem with projects
Measurements should induce the parts to do what is good for the system as a whole Measurements should direct managers to the point that needs their attention So often it occurs that we measure the wrong thing. The wrong measure leads to wrong behavior Tell me how you measure me and I will show you how I behave Tuesday, March 23, 2013 Presentation by James R. Burns

23 Presentation by James R. Burns
Measurements -5 -5 -5 +15 Tuesday, March 23, 2013 Presentation by James R. Burns

24 Presentation by James R. Burns
Cost vs Throughput Goldratt maintains that management in the cost world is a mirage efficiency becomes paramount local improvements are necessary to get global ones Goldratt suggests the managers should manage in the throughput world, a totally different paradigm must find the constraint--the weakest link concentrate on that By the way, what is the ultimate constraint??? Tuesday, March 23, 2013 Presentation by James R. Burns

25 Remember the five steps of TOC
IDENTIFY the project constraint--the critical path Decide how to EXPLOIT that constraint SUBORDINATE everything to that decision ELEVATE the systems’ constraint Go back to step 1, and find another constraint Tuesday, March 23, 2013 Presentation by James R. Burns

26 Presentation by James R. Burns
Safety Safety is however much time is added on to a task beyond its mean time of completion Tuesday, March 23, 2013 Presentation by James R. Burns

27 Probabilistic task durations
Late durations tend to accumulate and may increase the length of the project Early durations do not show up This explains why safety disappears Tuesday, March 23, 2013 Presentation by James R. Burns

28 Other problems with safety
Is wasted by the “student syndrome” Basically, this is procrastination Is wasted by multitasking (a person who works on several tasks at the same time) With each change of task, a set up is required Is wasted by dependencies between steps These dependencies cause delays to accumulate, but advances are wasted Delays get passed on; advances don’t Tuesday, March 23, 2013 Presentation by James R. Burns

29 Problems other than safety
Early start vs. late start Existing measurements are worthless because they are based on a cost world mentality, according to Goldratt Existing measurements (Earned Value Analysis) do not take into consideration the critical path We’re talking about BCWP, BCWS, ACWP, CV, SV, CPI, SPI, BAC, EAC, etc. Tuesday, March 23, 2013 Presentation by James R. Burns

30 Early Start vs. Late Start
B 5 A 5 E 10 D 10 C 10 Tuesday, March 23, 2013 Presentation by James R. Burns

31 How much Safety is there likely to be?
Will project professionals admit how much safety they are putting into their estimates? What happens when these professionals are asked to cut their durations by 10%, next time? These professionals want to be 100% sure of getting finished on time Therefore, the durations are likely to be twice as long as they should be So CUT THEM IN HALF Tuesday, March 23, 2013 Presentation by James R. Burns

32 Presentation by James R. Burns
Solutions Take the safety out of the individual tasks and put it at the end of the critical path in the time buffer, called a project buffer This means making the tasks roughly 50-60% as long as they would otherwise be. Tuesday, March 23, 2013 Presentation by James R. Burns

33 Presentation by James R. Burns
More solutions At the point where each feeding path intersects with the critical path, place another time buffer, called a feeding buffer. The feeding buffer protects the critical path from delays occurring in the corresponding non-critical paths. When resources are needed on the critical path, these resources are advised ahead of time exactly when they must make themselves available. When that time comes, they must drop everything else and do the required critical tasks. Tuesday, March 23, 2013 Presentation by James R. Burns

34 Measurement solutions
Measure progress only on the critical path; what percent of the critical path we have already completed. This is all we care about!! Have a project leader measure progress on a non critical path in terms of unused buffer days Tuesday, March 23, 2013 Presentation by James R. Burns

35 Shrinking the task time: Effects
There is less procrastination There is much more focus There is less multitasking Tuesday, March 23, 2013 Presentation by James R. Burns

36 Presentation by James R. Burns
More Suggestions Put your “BEST” people on the critical path Watch out for critical chains Tuesday, March 23, 2013 Presentation by James R. Burns

37 Presentation by James R. Burns
What are the ramifications of a delayed software product, intended for commercial sale? Less market share Less profit; maybe no profit Lower analyst profit expectations Declining share price Out of business? How many firms has Microsoft driven out of business? Ask Philippe Khan (founder of Borland) what the implications of getting a product late to the marketplace are Tuesday, March 23, 2013 Presentation by James R. Burns

38 What about Procurement
Most firms enter into LOSE/LOSE Strategies A fixed-price lowest bidder contract is LOSE/LOSE Strategy This forces Contractors to under bid their costs, hoping to make it back on the changes to the requirements that the customer will have to pay for Instead, Contractors should be induced to deliver product on time, with as much functionality as possible How would you do this? Tuesday, March 23, 2013 Presentation by James R. Burns

39 Presentation by James R. Burns
Tuesday, March 23, 2013 Presentation by James R. Burns