Download presentation
Presentation is loading. Please wait.
Published byGia Delafield Modified over 10 years ago
1
Utilizing IED Capability to Reduce Wiring Terrence Smith, GE Digital Energy Multilin Richard Hunt, GE Digital Energy Multilin Jakov Vico, GE Digital Energy Multilin
2
Introduction Reducing Wiring is not a new concept
3
Introduction Review of the Design/Installation Process A case study of a medium voltage breaker A case study of a transmission breaker A case study of a control IED as a transformer alarm aggregator
4
Introduction A case study of a high voltage circuit breaker using process bus. A look at the direction the industry will likely head. Rules we can develop from the case studies.
5
Introduction-How the design is communicated Typical Schematic Diagram
6
Introduction-How the design is communicated Typical Wiring Diagram
7
Introduction-How the design is communicated The design process
8
Introduction-How the design is communicated The design process
9
Case Study One- Medium Voltage Switchgear
10
Replace with IED Pushbutton
11
Case Study One- Medium Voltage Switchgear Replace with Latching Elements and IED Communications
12
Case Study One- Medium Voltage Switchgear Replace IED to SCADA communications
13
Case Study One- Medium Voltage Switchgear
14
Replaces Control Switch
15
Case Study One- Medium Voltage Switchgear Replaces SCADA Trip Contact
16
Case Study One- Medium Voltage Switchgear Replaces Lockout Relays
17
Case Study One- Medium Voltage Switchgear The new circuit is much simpler
18
Case Study One- Medium Voltage Switchgear The real value of internal lockout relays is seen in the close circuit
19
Case Study One- Medium Voltage Switchgear
20
Close Operands
21
Case Study One- Medium Voltage Switchgear Close Operands Block Close Logic
22
Case Study One- Medium Voltage Switchgear Optimization Benefits 1. Simpler Circuits meaning reduced design time, reduced wiring time, and reduced commissioning time. 2. Bench tested logic replaces wiring which reduces commissioning time. 3. Logic is repeatable and consistent.
23
Case Study One- Medium Voltage Switchgear Optimization Challenges 1. Cost of communications equipment, design, and installation 2. Operational challenges associated with process change.
24
Case Study Two – Breaker and a Half Scheme
26
62 wires and 124 terminations for one breaker of this scheme.
27
Case Study Two – Breaker and a Half Scheme
30
Case Study Three – Transformer Alarm Aggregator
31
Case Study Three – High Voltage Breaker with Process Bus
33
Future Directions – A station IED
34
Conclusions Rule #1: Wire a Process Value once and only once. Rule #2: If a function does not have to be wired, then dont.
35
35
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.