M+E Roof top clearance Project Overview Removal of all M+E items on the roof of the building to allow for cleaning and replacement of the roof. The works for the project included: Removal and installation of the solar thermal system Removal and installation of three air conditioning units Removal and replacement of three gas appliance flues Power flush and refill of solar thermal system Testing and commissioning New high temperature thermal insulation for solar thermal Project Value: £20,000.00 Project Team Client: Bridgend County Borough Council Main Contractor: Bridgend County Borough Council Consultant: N/A Project Manager: Mark Hillier-Rees Completion Date: July 2017 PROJECT PROFILE