2 Southampton Elementary School – Phase 2
New 10 Classroom Addition New Receiving Area Addition Addition / Alteration Main Office Site-work Improvements Toilet Room Reconstruction Art Room Alteration Computer Room Alteration Science Room Alteration Music and Band Room Alterations Interior Specialty Room Alterations Heating, Ventilation, Electrical and Plumbing Upgrades Ceiling and Lighting Replacements

3 Occupational Therapy Office
After Before

4 Fuel Oil Tank Replacement
Old Tank New Tank and Piping

5 Corridor Ceiling Replacement
New Third Floor Ceiling Existing Second Floor Ceiling New Corridor Wing Ceiling New Second Floor Ceiling

6 Interior Modifications at Library
New Openings From Library To New Computer Rooms Stage Removed at Library

7 Toilet Renovations Renovated Toilet Renovated Student Toilet
Renovated Faculty Toilet Renovated Nurses Toilet

8 Classroom Addition Site Excavation Site Demolition

9 Classroom Addition, Site Renovation and Playground
New Parking Lot Playground Area Egress Ramp at Addition Footing Formwork

10 Classroom Addition WEST ELEVATION NORTH ELEVATION – NEW CLASSROOM AREA

11 Southampton Intermediate School – Phase 3
SED is presently reviewing the drawings. Architect is reviewing SED comments. Architect to issue addendum to SED. Bidding of Phase 2 to be in October pending SED approval. Southampton High School – Phase 4 Architect working on construction documents. Final construction documents to be sent to SED beginning 2009. SED approval to take approximately 20 to 26 weeks.