Download presentation
Presentation is loading. Please wait.
1
EMIS 7307 Chapter 6
2
EMIS 7307 Chapter 6
3
EMIS 7307 Chapter 6 Fig 6.2 shows where the SEMP fits into the earliest program stages. Fig 6.5 has an example SEMP outline. Also see SEMP builder on the website. Excel based and asks lots of good questions. My SEMP preference follows in the next several slides.
4
EMIS 7307
5
EMIS 7307
6
Chapter 6 SEMP Outline 1. Scope 2. Program Management and Organization
EMIS 7307 Chapter 6 SEMP Outline 1. Scope 2. Program Management and Organization Overall organization Program management Subcontractor control Status reviews Contract Work Breakdown Structure (CWBS) Work authorization Schedule and resource (cost) management Risk management program
7
Chapter 6 SEMP Outline 3. System Engineering Product
EMIS 7307 Chapter 6 SEMP Outline 3. System Engineering Product System engineering approach Integrated process and product teams Interface to configuration management System engineering activities Technical Performance Measurement Interface to risk management Technical data interchange
8
Chapter 6 SEMP Outline 4. Integration of system engineering effort
EMIS 7307 Chapter 6 SEMP Outline 4. Integration of system engineering effort Requirements traceability System engineering integration activities 5. Technical reviews, major milestones, decision points, and their accomplishment criteria Program events Incremental review
9
EMIS 7307 Chapter 6 SEMP Outline 6. Critical technologies and research breakthroughs Critical technology selection approach Research breakthroughs Critical technologies 7. System test IPT roles in system I & T System development integration and test flow System test documentation
10
Chapter 6 SEMP Outline 8. Additional system engineering activities
EMIS 7307 Chapter 6 SEMP Outline Special system test and verification considerations Subcontractor roles and responsibilities Risk mitigation through system testing 8. Additional system engineering activities Long lead time activities Human system interface Make/buy approach Design to cost/life cycle cost
11
Chapter 6 Appendices 1. Reliability Program Plan
EMIS 7307 Chapter 6 Appendices 1. Reliability Program Plan Reliability program overview and tailoring Reliability reporting and organization Reliability schedule and milestones Program surveillance and control tasks Design and evaluation tasks Development and production testing
12
Chapter 6 Appendices 2. Maintainability Program Plan
EMIS 7307 Chapter 6 Appendices 2. Maintainability Program Plan Maintainability Program overview and tailoring Relationship to other plans Maintainability reporting and organization Maintainability schedule and milestones Program surveillance and control tasks Design and analysis tasks Evaluation and test
13
Chapter 6 Appendices 3. Producibility engineering program plan
EMIS 7307 Chapter 6 Appendices 3. Producibility engineering program plan Producibility engineering program management Producibility criteria Internal review process Producibility risk assessment Producibility tradeoffs for performance or schedule
14
Chapter 6 Appendices 4. Human engineering plan
EMIS 7307 Chapter 6 Appendices 4. Human engineering plan Legacy system human engineering User system interface standards Analysis and support to preliminary and detail design Prototyping Decision action diagram preparation Test and evaluation Human engineering milestones
15
Chapter 6 Appendices 5. Testability program plan
EMIS 7307 Chapter 6 Appendices 5. Testability program plan Organization and responsibilities Testability program schedules and milestones Testability design approach Testability analyses Testability design monitoring and control Testability verification
16
EMIS 7307 Chapter 6 Appendices 6. Technical performance measurement implementation plan Technical performance measurement Technical performance measurement process Technical performance measurement parameter list Technical performance measurement parameter dependency trees
17
EMIS 7307 Chapter 6 Appendices 6. Technical performance measurement implementation plan (continued) Technical performance measurement parameter profiles Tree parameter relationships Technical performance measurement interfaces
18
Chapter 6 Appendices 7. Program plan 8. Acronyms Term definitions
EMIS 7307 Chapter 6 Appendices 7. Program plan Term definitions Program events definition System flow Major review content Program entry accomplishments and criteria Program exit accomplishments and criteria 8. Acronyms
19
Chapter 6 Figure 6.40 shows SEMP’s central role.
EMIS 7307 Chapter 6 Figure 6.40 shows SEMP’s central role. Along with the SEMP comes the need for the work breakdown structure (WBS). Breaks the work into manageable pieces. Provides specific places to accumulate costs. FFP internal use. CPF customer and internal use.
20
EMIS 7307
21
EMIS 7307 Chapter 6
22
EMIS 7307 Chapter 6
23
EMIS 7307 Chapter 6
24
EMIS 7307 Chapter 6
25
Chapter 6 Statement of Work (SOW) Shorter is better
EMIS 7307 Chapter 6 Statement of Work (SOW) Shorter is better Make sure that the work you want to be chargeable under the contract is included. Converse is true too! If you are unsure and you trust your contractor then perhaps some vagueness is prudent. Otherwise, frequent SOW changes, which are as ‘painful’ as contract changes, will be necessary.
26
EMIS 7307 Chapter 6 SOW (cont’d) CORs, DLA, and DCMA are responsible to make sure work performed is in scope. Fig 6.6 contains typical System Engineering tasks for a SOW.
27
EMIS 7307
28
Chapter 6 Program schedules, things to know.
EMIS 7307 Chapter 6 Program schedules, things to know. Based on experience and educated estimates. When using PERT/CPM first build a network of activities that shows the interrelated events through the life of the program Start at the end and work backwards. Next develop three estimates: the optimistic, pessimistic and the most likely times for each event.
29
The WBS is the Foundation for Project Scheduling
EMIS 7307 Chapter 6 The WBS is the Foundation for Project Scheduling Project Subsystem A Subsystem B = = Assembly A1 Assembly A2 CS Component B1 Test B1 Test B1 Sub Assy A11 Sub Assy A12 Sub Assy A13 Code B1 Code B1 = = Design B1 Design B1 Test A2 Test A2 Build A2 Build A2 Design A2 Design A2 Test A1 Test A12 Build A2 Build A12 Design A1 Design A12
30
Chapter 6 Program schedules—things to know (cont’d).
EMIS 7307 Chapter 6 Program schedules—things to know (cont’d). What does the term “critical path” mean? Longest or shortest path through the network? See Fig 6.19 on page 300. What does the term “slack” mean? What does the term “crunch” mean?
31
EMIS 7307
32
Chapter 6 Cost estimates. See Figure 6.27
EMIS 7307 Chapter 6 Cost estimates. Rough order of magnitude (ROM) +/- 30% . Distressing when proposals are always more than ROM! Cost estimates are expected to be +/-5%. See Figure 6.27 Typically where is most the cost? See last paragraph of section
33
EMIS 7307
34
EMIS 7307
35
Chapter 6 Risk Avoidance Control Acceptance Transfer
EMIS 7307 Chapter 6 Risk Avoidance Control Acceptance Transfer See pages 138, 139 in SE Handbook.
36
Technology Readiness Assessment
EMIS 7307 Technology Readiness Assessment Why and How We Use Technology Readiness Levels (TRL). Technology Readiness Levels (TRL) 1-9 as defined by NASA. Goal is for all high-risk items to reach TRL 5/6 by PDR. A project that reaches TRL 6 or higher by the start of Phase C/D is likely to stay within 15% of the baseline cost estimate made at the start of Phase C/D. (NASA analysis)
37
Pre-Phase A = Advanced studies = Preconceptual planning
EMIS 7307 PROJECT CYCLES Pre-Phase A = Advanced studies = Preconceptual planning Phase A = Concept exploration = Conceptual design = Preliminary analysis Phase B = Preliminary design = Product/Program definition Phase C = Detailed design Phase D = Construction = Engineering and manufacturing development Phase E = Operations
38
EMIS 7307
39
EMIS 7307 Note: The line between the “technology risk factor ” and the “design and engineering risk factor” is somewhat fuzzy since both involve development. The “technology risk factor” focuses on research and developing the application while the “design and engineering risk” focuses on the detailed implementation of the end-item.
40
EMIS 7307
41
EMIS 7307 Chapter 6 BRASSBOARD - An experimental device (or group of devices) used to determine feasibility and to develop technical and operational data. It normally is a model sufficiently hardened for use outside of laboratory environments to demonstrate the technical and operational principles of immediate interest. It may resemble the end item, but is not intended for use as the end item. It is normally built during Advanced Studies / Pre-Conceptual and Conceptual Design /Preliminary Analyses Phases and may be continued in the Preliminary Design Phase. BREADBOARD - An experimental device (or group of devices) used to determine feasibility and to develop technical data. It normally is configured only for laboratory use to demonstrate the technical principles of immediate interest. It may not resemble the end item and is not intended for use as the projected end item. It is normally built during Advanced Studies or Pre-Conceptual and Conceptual Design Phases.
42
Analysis--Risk Rating Matrix
EMIS 7307 Chapter 6 Analysis--Risk Rating Matrix
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.