Well Repair Installation of Well Liners
Grouting off poor water producing areas Modifying and Upgrading Well Heads Unique Design Build Projects
2
Consider all the Costs of a New Well
Making repairs to a well is often the best option vs. drilling & constructing a new well Consider all the Costs of a New Well Testing and Drilling Modifying piping and infrastructure for new well Modifying Permit to Take Water and C of A Associated Engineering Costs Abandoning the old well Time It’s going to take time to do all this, repairing almost always less time intensive
3
Well Casings and Screens Corrode Over Time
Example of well casing with holes in it
4
Other examples of casing failure
5
Other examples of casing failure
Example of well casing with holes in it (side scan)
6
By lining the well with a new steel well casing
How do we repair this? By lining the well with a new steel well casing
7
General Liner Installation Procedure
Step 1 Install liner Step 2 Install temporary packer Step 3 Fill space between liner and old well casing with grout Step 4 Remove Packer
8
Attaching Liner to Crane
9
Installing Grout Lines
We can use grouting lines as small as 3/8” which allows us to install a relatively large diameter liner and keeps the functional diameter of the well at a maximum which allows more pump options. We can usually line a well with 50mm smaller nominal diameter liner than the original casing.
10
We usually use stainless steel for long life
11
Lifting the stainless steel liner
12
To install the liner we need the same amount of room as installing a pump
13
Liner Installation
14
The process takes about a week to complete
15
Joining two pieces of liner
16
Joining two pieces of liner
17
All casing welds made by certified welders
18
All casing welds made by certified welders
19
40m of Schedule 10 304 SS in place and ready for inspection and packer installation
20
But first we take a look with the camera to make sure everything is in the right place
21
Camera Uses We use the camera several times in the process
during grout line installation during the grouting process upon completion to make sure the liner was installed as designed
22
Next we install the packer to seal the annular space at the base of the liner
23
We have sliding head packers that can line a well up to 24” in diameter
24
Packer Installation
25
Packer Installation The packer being installed on steel pipe that goes all the way through the packer so we can inspect the base of the liner during grouting to check for leaks
26
Packer installed and ready for grouting
27
Progressive cavity high pressure grout pump and tandem mixer
Allows us to grout through small grout lines
28
Custom Grouting Special formulated grouts have been specifically designed for Lotowater by a grouting engineer and expert in the grouting field. Custom grouts are often designed for unusual or difficult conditions. Special grouts allow us to grout through small lines
29
A new well with liner, good for another 50 years?
30
Well Head Upgrades & Designs
31
Sometimes wells need to be upgraded to keep up with new regulations
In this case, a new pitless adapter was installed Wellhead not in compliance with new regulations New well head in compliance with MOE well regulations
32
Sometimes we need to go back to the drawing board
Well head is under here, taking water levels from this well was virtually impossible, let alone removing the pump
33
For a well guy this is a real pain
34
Well Head Design We start with a plan
35
We end up with something much better and much more practical
36
Having an experienced contractor help with wellhead design maximizes functionality
37
Unique Design Build Projects
We often team up with engineering consulting companies on projects where wells are an integral component Our experience and knowledge is useful in coming up with functional and economic alternatives for wells
38
Well 2 in building Well head was in flood plain and susceptible to flooding
39
Well was also flowing artesian so special considerations had to be made to control the flow
40
We worked with the engineer on the project and came up with this design
41
Putting in a new custom design pitless adapter
42
The well head is above the 100 year flood level and meets all regulations
43
Upgrade Benefits No more worrying about: Flooding Heating a building
Accessing the well for service
44
As constructed and working great