2017 Total Revenues were: $9,165,946.06 Revenues by program:
*Landfill $8,127, *Transfer Stations $422, *Interest/sale of assets $389, *Recycling $9, *HHW $46, *Education $29,761.37 *North Front Range Regional Wasteshed $40,000 2017 Total Expenses were: $5,496,341.12 Expenses by major category: *Operating $2,771,520 *Personnel $2,011,701 *North Front Range Regional Wasteshed $273,496.81
4
Airspace Remaining at Landfill
1998 Design Mod 2004 Final Expansion Expansion
5
2017 Solid Waste Fund Balance: $37,204,692 $8,000,000 reserved closure and post closure
6
Goals & Objectives Goal #1 Goal #2 Goal #3 Goal #4
Establish a comprehensive, regional solid waste materials management system by 2025 that is implemented in an economically, environmentally and socially sustainable manner. Goal #2 Create a comprehensive solid waste materials management plan and implement programs and facilities that reflect the needs and desires of users. Goal #3 Develop a set of waste diversion/reduction goals that are adopted and implemented by all jurisdictions in the Wasteshed. Goal #4 Develop a strong public education and outreach program that is consistent throughout the Wasteshed.
7
Infrastructure Options for Consideration
Status Quo Central Transfer Station New County Landfill Material Recovery Facility (Clean) Yard Waste Organics Processing Facility C&D Processing Facility Energy from Waste Facility (Direct Combustion) Mixed Waste Processing (Dirty MRF) Aerobic Composting Including Food Waste Anaerobic Digestion Refuse Derived Fuel (RDF) Processing
8
Review of Solid Waste Volumes at the Larimer Co Landfill
9
Infrastructure Analysis – Tier 1 Recommendations for New Facilities
Capital Costs Cost per ton* Benefit Cost Ratio Waste Volume Managed (%) Central Transfer Station $14.3M $31 / Ton 1.11 100% New County Landfill (Accepting Transferred Materials Primarily) $11.7M (1st Phase) $17 / Ton 2.13 Construction & Demolition (C&D) Processing $13.7M $30 / Ton 2.05 31%** Yard Waste Open Wind-Row Composting $10.6M $27 / Ton - $28 / Ton 5.89 13% Food Waste Static Aerated Bin Composting $33 / Ton - $38 / Ton 3.94 * Cost per ton does not include general administrative costs ** Residual disposal required
10
Population Zone/Direct Haul Map
11
Comprehensive Solid Waste System – Top 5
New County Landfill Yard Waste Organics Processing Facility Construction & Demolition (C&D)Processing Facility Central Transfer Station Existing MRF Transfer Aerobic Composting Including Food Waste
12
Solid Waste Processing and Landfill Diversion