1
November 2007 Project: IEEE P Working Group for Wireless Personal Area Networks (WPANs) Submission Title: [TG3c Schedule] Date Submitted: [18 July, 2007] Source: [M. Mc Laughlin, DecaWave] Address [25 Meadowfield, Sandyford, Dublin 18, Ireland] Voice:[], FAX: [], Re: [] Abstract: [Proposal for c Timeline] Purpose: [Proposal for c Timeline] Notice: This document has been prepared to assist the IEEE P It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Release: The contributor acknowledges and accepts that this contribution becomes the property of IEEE and may be made publicly available by P
2
Comparison: TG4a Timeline TG3c Timeline
November 2007 Comparison: TG4a Timeline TG3c Timeline
3
November 2007 Baseline 1st Letter Ballot
4
TG3c Schedule November 2007 Project timeline based on 05/311r16
Baseline 1st Letter Ballot x
5
How do they compare? – 4a TG4a was completed in record breaking time.
November 2007 How do they compare? – 4a TG4a was completed in record breaking time. Baseline complete: March 2005 Ready for letter ballot: November 2005 Only 8 Months to a Iron out the bumps! Phew, Well done guys! A tight schedule but in the end: A quality standard
6
How do they compare? – 3c TG3c Targets
November 2007 How do they compare? – 3c TG3c Targets Baseline complete: November 2007 If we do as well as TG4a, i.e. only 8 Months Ready for letter ballot: July 2008. This is a tough target. 3c is much more complex than 4a Our Actual Target Ready for letter ballot: December 2007 Whatwasthat!!!
7
Summary Aggressive Timetable Yes, that’s good.
November 2007 Summary Aggressive Timetable Yes, that’s good. We need to keep our foot to the floor But… We should not rush out a draft standard We should not even think about having a draft standard ready for letter ballot before end of July 2008 meeting