Software Project Management
Session 1: Introduction, Fundamentals, Classic Mistakes Q7503 Principles of Project Management, Fall 2002
2
Q7503 Principles of Project Management, Fall 2002
Today Course basics, administrative items Introductions Fundamentals Classic Mistakes No lab today More lab in later term Q7503 Principles of Project Management, Fall 2002
3
Q7503 Principles of Project Management, Fall 2002
Syllabus Review Grades Exams Assignments Project Class participation Sessions Class web site Broadest material in program Walk away from this course with skills applicable to all forms of projects But software and IT projects in particular They have special characteristics Will bring in show & tell from my current projects Often discuss material in relation to your projects We can Refine the curricula Questions? Q7503 Principles of Project Management, Fall 2002
4
Q7503 Principles of Project Management, Fall 2002
Textbooks Required texts “Rapid Development”, Steve McConnell “Information Technology Project Management”, Kathy Schwalbe These provide two very different viewpoints In-the-trenches vs. PMI textbook perspective Recommended reading “Quality Software Project Management”, D. Shafer “Software Project Survival Guide”, Steve McConnell “Peopleware”, T. DeMarco and T. Lister Not yet at bookstore Amazon discounted Show texts to class Only selections from each Chosen for balance and relevance Going to read the Important sections and the Fun sections Expose to a variety of practices and viewpoints I will put together a reading list for reference Online resources (URLs) 100’s of books on topic Quality range of titles (age, size too) Different Subject leanings (general, technical, people, process) Questions? Q7503 Principles of Project Management, Fall 2002
5
Q7503 Principles of Project Management, Fall 2002
Basics Essential elements of software project management Practical, rapid development focus Real-world case studies And other examples like job interviews Highly interactive Dry as toast? 2 exams 4 or 5 small homework assignments MS Project for your ‘book’ Small class == large input Grade depends on participation Questions? Q7503 Principles of Project Management, Fall 2002
6
Q7503 Principles of Project Management, Fall 2002
My Background 20 years, 70 projects Bell Labs, Hughes Aircraft, Solomon, Electronic Arts, MTV, numerous startups Projects of all shapes and sizes Technical questions allowed (after class) Engineer, team lead, project manager, division head Seen the spectrum of types and sizes of IT projects “Hands-on” PM Currently consulting Step outside of PM role Questions? Q7503 Principles of Project Management, Fall 2002
7
Q7503 Principles of Project Management, Fall 2002
Your Background Name Day Job or Equivalent Final Project Project Management Experience Industry Experience Optional: Expectations & goals from the class Review sign-up sheet Where are they in their ‘program’ or term Q7503 Principles of Project Management, Fall 2002
8
Q7503 Principles of Project Management, Fall 2002
The Field Jobs: where are they? Professional Organizations Project Management Institute (PMI) (pmi.org) Software Engineering Institute (SEI) IEEE Software Engineering Group Certifications PMI PMP The “PMBOK” – PMI Body of Knowledge Tools MS Project dice.com search “project management” See everything from this class Bridge Technical and non-technical Other Certs don’t matter Hundreds of PM programs like MS-Project Project: the illusion of control Q7503 Principles of Project Management, Fall 2002
9
Q7503 Principles of Project Management, Fall 2002
The Field Part 2 Average PM salary $81,000 Contract rates for PM’s can match techies PMI certification adds avg. 14% to salary PMI certs, 1993: 1,000; 2002: 40,000 Other cert: CompTIA Project+ Links: See class web site Q7503 Principles of Project Management, Fall 2002
10
Q7503 Principles of Project Management, Fall 2002
Job Fundamentals Skills required PM Positions and roles The process Q7503 Principles of Project Management, Fall 2002
11
Project Management Skills
Leadership Communications Problem Solving Negotiating Influencing the Organization Mentoring Process and technical expertise Q7503 Principles of Project Management, Fall 2002
12
Project Manager Positions
Project Administrator / Coordinator Assistant Project Manager Project Manager / Program Manager Executive Program Manager V.P. Program Development Q7503 Principles of Project Management, Fall 2002
13
Software Project Management
Q7503 Principles of Project Management, Fall 2002
14
PM History in a Nutshell
Birth of modern PM: Manhattan Project (the bomb) 1970’s: military, defense, construction industry were using PM software 1990’s: large shift to PM-based models 1985: TQM : Re-engineering, self-directed teams : Risk mgmt, project offices 2000: M&A, global projects Q7503 Principles of Project Management, Fall 2002
15
Q7503 Principles of Project Management, Fall 2002
What’s a project? PMI definition A project is a temporary endeavor undertaken to create a unique product or service Progressively elaborated With repetitive elements A project manager Analogy: conductor, coach, captain Temporary: can be years Result can be lasting Team can be temporary Finite duration Ex: thousands of buildings, but each is unique Scope s/b constant even as elaboration happens Q7503 Principles of Project Management, Fall 2002
16
Project vs. Program Management
What’s a ‘program’? Mostly differences of scale Often a number of related projects Longer than projects Definitions vary Ex: Program Manager for MS Word Q7503 Principles of Project Management, Fall 2002
17
Interactions / Stakeholders
As a PM, who do you interact with? Project Stakeholders Project sponsor Executives Team Customers Contractors Functional managers managing all stakeholder Expectations is challenging – conflict Q7503 Principles of Project Management, Fall 2002
18
Q7503 Principles of Project Management, Fall 2002
PM Tools: Software Low-end Basic features, tasks management, charting MS Excel, Milestones Simplicity Mid-market Handle larger projects, multiple projects, analysis tools MS Project (approx. 50% of market) High-end Very large projects, specialized needs, enterprise AMS Realtime Primavera Project Manager Q7503 Principles of Project Management, Fall 2002
19
Q7503 Principles of Project Management, Fall 2002
Tools: Gantt Chart Q7503 Principles of Project Management, Fall 2002
20
Tools: Network Diagram
Q7503 Principles of Project Management, Fall 2002
21
Q7503 Principles of Project Management, Fall 2002
PMI’s 9 Knowledge Areas Project integration management Scope Time Cost Quality Human resource Communications Risk Procurement If you study for the PMI certification you’ll need to know these Q7503 Principles of Project Management, Fall 2002
22
Q7503 Principles of Project Management, Fall 2002
First Principles One size does not fit all Patterns and Anti-Patterns Spectrums Project types Sizes Formality and rigor Like families, each dysfunctional in it’s own “special way” Classic Mistakes later == Anti Different sizes need different choices from the PM Q7503 Principles of Project Management, Fall 2002
23
Q7503 Principles of Project Management, Fall 2002
Why Rapid Development Faster delivery Reduced risk Increased visibility to customer Don’t forsake quality Q7503 Principles of Project Management, Fall 2002
24
Q7503 Principles of Project Management, Fall 2002
Strategy Classic Mistake Avoidance Development Fundamentals Risk Management Schedule-Oriented Practices McConnell refers to “Pillars” These provide balance Q7503 Principles of Project Management, Fall 2002
25
Four Project Dimensions
People Process Product Technology Peopleware issues 10-to-1 difference in Dev productivity Teams 3 or 5 to 1 diff Process Dev basics, risk mgmt, QA, lifecycle planning, customer orientation Product Most tangible dimension Technology Q7503 Principles of Project Management, Fall 2002
26
Q7503 Principles of Project Management, Fall 2002
Trade-off Triangle Fast, cheap, good. Choose two. Q7503 Principles of Project Management, Fall 2002
27
Q7503 Principles of Project Management, Fall 2002
Trade-off Triangle Know which of these are fixed & variable for every project Q7503 Principles of Project Management, Fall 2002
28
Q7503 Principles of Project Management, Fall 2002
People “It’s always a people problem” Gerald Weinberg, “The Secrets of Consulting” Developer productivity: 10-to-1 range Improvements: Team selection Team organization Motivation Teams: 5-to-1 range Q7503 Principles of Project Management, Fall 2002
29
Q7503 Principles of Project Management, Fall 2002
People 2 Other success factors Matching people to tasks Career development Balance: individual and team Clear communication Q7503 Principles of Project Management, Fall 2002
30
Q7503 Principles of Project Management, Fall 2002
Process Is process stifling? 2 Types: Management & Technical Development fundamentals Quality assurance Risk management Lifecycle planning Avoid abuse by neglect cut time-to-market Improve quality Q7503 Principles of Project Management, Fall 2002
31
Q7503 Principles of Project Management, Fall 2002
Process 2 Customer orientation Process maturity improvement Rework avoidance Q7503 Principles of Project Management, Fall 2002
32
Q7503 Principles of Project Management, Fall 2002
Product The “tangible” dimension Product size management Product characteristics and requirements Feature creep management Q7503 Principles of Project Management, Fall 2002
33
Q7503 Principles of Project Management, Fall 2002
Technology Often the least important dimension Language and tool selection Value and cost of reuse Q7503 Principles of Project Management, Fall 2002
34
Q7503 Principles of Project Management, Fall 2002
Planning Determine requirements Determine resources Select lifecycle model Determine product features strategy Q7503 Principles of Project Management, Fall 2002
35
Q7503 Principles of Project Management, Fall 2002
Tracking Cost, effort, schedule Planned vs. Actual How to handle when things go off plan? Q7503 Principles of Project Management, Fall 2002
36
Q7503 Principles of Project Management, Fall 2002
Measurements To date and projected Cost Schedule Effort Product features Alternatives Earned value analysis Defect rates Productivity (ex: SLOC) Complexity (ex: function points) Q7503 Principles of Project Management, Fall 2002
37
Technical Fundamentals
Requirements Analysis Design Construction Quality Assurance Deployment Q7503 Principles of Project Management, Fall 2002
38
Q7503 Principles of Project Management, Fall 2002
Project Phases All projects are divided into phases All phases together are known as the Project Life Cycle Each phase is marked by completion of Deliverables Identify the primary software project phases Q7503 Principles of Project Management, Fall 2002
39
Lifecycle Relationships
Q7503 Principles of Project Management, Fall 2002
40
Seven Core Project Phases
Q7503 Principles of Project Management, Fall 2002
41
Q7503 Principles of Project Management, Fall 2002
Project Phases A.K.A. Q7503 Principles of Project Management, Fall 2002
42
Q7503 Principles of Project Management, Fall 2002
Phases Variation Q7503 Principles of Project Management, Fall 2002
43
Q7503 Principles of Project Management, Fall 2002
36 Classic Mistakes McConnell’s Anti-Patterns Seductive Appeal Types People-Related Process-Related Product-Related Technology-Related Gilligan’s Island Seductive: good reason for decisions at the time Some are IT, most not We’ll visit these throughout course Gilligan’s Island: new scheme, get off island, seems to work, then fails Being aware can help prevent Class discussion Q7503 Principles of Project Management, Fall 2002
44
People-Related Mistakes Part 1
Undermined motivation Weak personnel Weak vs. Junior Uncontrolled problem employees Heroics Adding people to a late project Motivation: studies show has largest impact Don’t undermine Morale 2nd greatest influence on productivity Junior != bad Uncontrolled: most common developer complain about their managers Heroics. Company hostage. “Can-do”, “how high” attitudes Brooks, reading assignment Q7503 Principles of Project Management, Fall 2002
45
People-Related Mistakes Part 2
Noisy, crowded offices Customer-Developer friction Unrealistic expectations Politics over substance Wishful thinking 60%of developers feel unsatisfactory environment: need quite and privacy MS offices Friction: classic differing viewpoints Results in ‘poor communication’ Passive-aggressive Realistic Expectations: 1 of top 5 reasons for success of in-house projects Perception woe Politics Managing-up Wishful Cognitive dissonance Closing your eyes and hoping McConnell: maybe causes the most problems in software development Q7503 Principles of Project Management, Fall 2002
46
People-Related Mistakes Part 3
Lack of effective project sponsorship Lack of stakeholder buy-in Lack of user input Sponsor: a must, no power All players must buy-in User input: Survey: number 1 reason for success W/O input: guessing Q7503 Principles of Project Management, Fall 2002
47
Process-Related Mistakes Part 1
Optimistic schedules Insufficient risk management Contractor failure Insufficient planning Abandonment of plan under pressure Similar to wishful thinking Puts unnecessary pressure Risk Mgmt: Risks will manage you Contractor: late, poor quality, or fails to meet specifications Requires lots of management Insufficient planning: “if you don’t care where you’re going, any plan will do” Abandonment Out the window Fall into code-and-fix mode Q7503 Principles of Project Management, Fall 2002
48
Process-Related Mistakes Part 2
Wasted time during fuzzy front end Shortchanged upstream activities Inadequate design Shortchanged quality assurance fuzzy: before sign-off Upstream: Lack of analysis and design 10 to 100 times more costly 5 hrs vs. 50 Design: Seen schedules w/o it at all QA: Seems easy to compress 1 day QA == 3 to 10 later Q7503 Principles of Project Management, Fall 2002
49
Process-Related Mistakes Part 3
Insufficient management controls Frequent convergence Omitting necessary tasks from estimates Planning to catch-up later Code-like-hell programming Management controls Need to be able to track We’ll cover lots of these PMI Convergence Waste of time Missing tasks Often 20-30% of a schedule Catch-up later How many times have you seen a project catch-up? Only by all-nighters Like hell “Entrepreneurial” approach See catch-up later Q7503 Principles of Project Management, Fall 2002
50
Product-Related Mistakes
Requirements gold-plating Gilding the lily Feature creep Developer gold-plating Beware the pet project Push-me, pull-me negotiation Research-oriented development Gold Gilding the lily Performance is required more often than need be Feature creep 25% average change in req. Dev. Gold Nifty new technology Pet project Push-me Slip schedule + add features Research vs. Development Q7503 Principles of Project Management, Fall 2002
51
Technology-Related Mistakes
Silver-bullet syndrome Overestimated savings from new tools and methods Fad warning Switching tools in mid-project Lack of automated source-code control who’s heard of ‘silver bullet’ (not the beer) SCM Jones: 10% month, I see more Q7503 Principles of Project Management, Fall 2002
52
Q7503 Principles of Project Management, Fall 2002
Reading McConnell: Chapters 1-4 We covered most of Ch 3 today Schwalbe: chapters 1-2, 11 ( ) We covered some here Brooks Overview Q7503 Principles of Project Management, Fall 2002