1 July 12, 2018

2

3 Updates Phase 1.1 Phase 1.2 Plaza improvements Arsenal Pump Station
Design Status Construction Activities Calder Alley Archaeological Mitigation Commerce Street Closure Stakeholder Coordination

4 Phase 1.1 Update Plaza de Fundación underwent modifications to prevent swimming Grate in the manantial raised to a shallower depth Center channel reduced to a shallow swale between the manantial and cascadia pools Leveling of plaza surface to improve ADA accessibility Arsenal Pump Station Completion

5

6

7

8

9

10 Phase 1.2 Construction Update
Early Work Package 11: Demolition and Utility relocation Utility relocation work ongoing Calder Alley mitigation plan to begin 7/16

11

12 Phase 1.2 Construction Update
Early Work Package 12: Heavy Civil Construction Drilled pier construction on site of former Dollar General building

13

14 Commerce Street Closure
Full closure began June 25 3-month duration One lane open beginning late September 13-month duration Bridge demolition commenced

15

16 Phase 1.2 Design Update 100% design progress halted to allow design team to focus on Phase 1.1 modifications 100% design submittal July 20th Guaranteed Maximum Price submittal late September Coordination with SDJV ongoing Carrie Brown will work with design team to identify public art opportunities

17 Partner Coordination Executive Committee
David Smith, County Manager, Bexar County Lori Houston, Assistant City Manager, City of San Antonio Mike Frisbie, Director, Transportation and Capital Improvements, City of San Antonio Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – July 20th

18 QUESTIONS & COMMENTS