ELCITA Update January 2016
2
Estate Management Skywalk E – Toilets
Contract Awarded to M/s mayaPRAXIS to provide Architectural & Structural feasibility report of Skywalk system for Electronics city phase 1. E – Toilets 12 e-toilets operational and 4 more e-toilets yet to start. Under Ground Drainage System EI Technologies have been asked to revised UGD design
3
Estate Management Estate survey
Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 70 % completed. Improvement of road geometry at WIPRO junction Drawings are approved by WIPRO and vendor finalization for Construction of compound wall in progress. Proposed Concrete Road along Doddanagamangala Village – Approval awaited.
4
Tessolve/ Edizi Tools Road
Estate Management Permanent Works - Under Progress WIPRO Neeladri Road Tessolve/ Edizi Tools Road
5
Fire station to Haritha IT Park Road
Estate Management Asphalting Works - Under Progress Fire station to Haritha IT Park Road Y Junction Road
6
Bhavani Industries Road
Estate Management Permanent Works - Under Progress Quasitum Road Bhavani Industries Road
7
Estate Management Permanent Works – Under Progress C-Dot D-Mart Road
E-city Survey
8
Estate Management Maintenance – Under Progress Cyient Drain
Svenska Drain
9
Estate Management Maintenance – Under progress
Extension of Column at Wipro gate No 15 RMU Wipro gate No15
10
Estate Management Road Maintenance Work – Completed
Asphalting from Tescom to Veerasandra road Kerbstone laying from Tescom to Veerasandra road
11
Pot holes filling work completed at various location
Estate Management Raod Maintenance Work– Completed Pot holes filling work completed at various location
12
Estate Management Maintenance – Completed
Wipro Concrete Foundation base breaking Compound wall for 300KLD STP
13
Tree root rermoving all round Infosys Hirandhani Building
Estate Management Maintenance – Completed Tree root rermoving all round Infosys Hirandhani Building
14
Bus Stop below the flyover for BMTC buses
Estate Management Improvement Work– Completed Bus Stop below the flyover for BMTC buses
15
20 feet deep well Rainwater Harvesting Pit at Various locations
Estate Management Maintenance works – Completed 20 feet deep well Rainwater Harvesting Pit at Various locations
16
Supply & Erection of E-waste Shed at SWM facility
Estate Management Maintenance Works – Under Progress Supply & Erection of E-waste Shed at SWM facility
17
Estate Management Permanent Works – Under Progress
Construction of 300KLD Conventional STP in ELCIA Park . Total Project Cost - Rs. 75,72,798/- (Including Civil & STP works)
18
Estate Management Tender Published
Providing and laying of Asphalting using 60/70 grade bitumen from Wipro Gate 5 to Gate 16 along Neeladri Road, Electronics City Phase 1, Bangalore –
19
Estate Management Contracts Awarded
Proposed Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from Fire Station to Canara bank Road junction, Electronics City Phase 1, Bangalore Providing and laying of Asphalting using 60/70 grade bitumen from C-DOT to D-Mart Road Junction Tessolve to Edizi Tools road
20
Estate Management Contracts on Anvil
Providing and laying of Asphalting using 60/70 grade bitumen from Hp Avenue Fire Station to Canara Bank Road junction Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road
21