Southern Delivery System
NSPE-Colorado State Meeting February 19, 2010
2
Our future depends on it
SDS: Our Future Depends on It Regional project Colorado Springs Fountain Security Pueblo West Our future depends on it Growing community Drought protection System Reliability Long-term Water Supply 2
3
Colorado Springs Water System
3
4
SDS Components 62 miles underground pipeline 3 pump stations
Water treatment plant Capacity = 78 mgd Firm yield = 42,400 acft/yr Primary source = Reuse by exchange of Fry-Ark Project water SECURITY FOUNTAIN 4 4
5
SDS Milestones SDS Today Record of Decision Pueblo County 1041 Permit
Colorado Springs Utilities Board Approval Fountain Creek District Board approval 5 5 5 5
6
Approvals Underway Next Steps El Paso County permit
Army Corps 404 permit State 401 certification Fish & Wildlife Mitigation Plan Reclamation contracts 6
7
2016 Implementation Schedule
1041 Permit Condition Record of Decision Pueblo County 1041 Permit MAJOR PERMITS ENGINEERING LAND ACQUISITION CONSTRUCTION START-UP SDS IN SERVICE 2016 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 7 7
8
Regional Economic Benefits
SDS Economic Benefits: Phase 1 Construction Total Construction Costs $550 million – Portion spent on construction labor $160 million Average employment 380 workers Peak employment 700 workers Estimated workforce by year: 2010 – – – 510 2011 – – – 80 2012 – 290 We expect about 50 to 75 percent of the labor force to come from the region. 8
9
Construction/Contracting
Procurement outreach Contractor workshops beginning this year Register at csu.org 9 9
10
Email us: sdsinfo@csu.org www.sdswater.org
Follow our progress Project eNewsletter us: 10 10 10 10
11
Questions