Download presentation
Presentation is loading. Please wait.
1
Lucius Skid Pics
2
SET UP CUPS ON SKID BEAMS TO FRAME UP LOWER LEVEL FOR HP SKID
3
SHOP PREP STIFFNERS FOR HP MANIFOLD SKID
4
BEAMS CUT AND COPED FOR LOWER LEVEL HP MANIFOLD SKID
5
DRAIN TROUGHS WELDED FOR COOLING MEDIUM SKID
6
ICP SPOOLS IN X-RAY AREA FOR LP SKID
7
LOWER LEVEL FRAMING FOR FUEL GAS SKID
8
LOWER LEVEL FRAMING PLATED FOR COOLING MEDIUM SKID
9
FRAMING UPPER LEVEL FOR COOLING MEDIUM SKID
10
FITTING 10” PIPE HALF BEAM STIFF. INTO LOWER LEVEL COOLING MEDIUM
11
WELDING BEAMS INTO LOWER LEVEL FRAMING FOR (LP) SKID
12
PIPE SUPPORTS FOR (LP) SKID MODULE
13
BEAMS CUT AND COPED FOR UPPER LEVEL (LP) SKID
14
ICP SPOOLS FOR COOLING MEDIUM SKID IN X-RAY AREA