Team Mate Conceptual Design Review
Fall 2010 Rev A Team Mate Conceptual Design Review Amelia Weller, Erick Chewakin, Will Hakes, Emma Mossinger, Brendon Barela, Jason Schelz, Ethan Long 9/16/10
2
Our objective is to study the amounts of UV radiation in the upper stratosphere.
We believe that we will find an increased amount of UV radiation as compared to previous years’ data. We are doing this because we think that it would be fascinating to see the difference in UV radiation with the solar flare that has occured Mission Overview
3
We will complete our mission by using a light to frequency converter in conjunction with an Arduino microcontroller that will allow the payload to take data points on the amount of UVA radiation present in the atmosphere. Parts Arduino microcontroller Light to frequency converter Camera HOBO Design
4
Design cont.
5
Management Team Members Team Member Address Phone # Specialty
Assistant Position Amelia Weller Cockerell 109 (775) Team Leader and Budget/Schedule Testing Brendon Barela Crosman 104 (303) C&DH and Science Emma Mossinger 203 (925) Testing Lead Structures/Thermal Ethan Long Aden (303) Structures/Thermal Lead Electrical Erick Chewakin Brackett 206 (719) Electrical Lead Jason Schelz 120 (203) C&DH Structure/Thermal Will Hakes 004 (970) Science Lead Management Team Members
6
Management Con’t Schedule Date Time What 9/7 6:45 PM First Meeting 9/9
Begin Proposal 9/10 2:20 PM Assign Specializations 9/14 Team Meeting (design complete) 9/15 6:30 PM Team Meeting (proposals complete) 9/16 7:00 AM Proposals AND Presentations Due 9/21 At apt Order Hardware 9/28 7:00 PM Team Meeting (begin construction) 9:30 AM Heater Due 10/5 DD Rev A/B and CDR Presentation Due Team Meeting 10/12 Team Meeting (prototyping design complete) 10/19 Team Meeting (cold test complete) 10/26 Pre-Launch Inspection 10/28 Mission Test 11/2 LLR Presentations and DD Rev C Due Team Meeting (design review) 11/5 Balloon Weigh-in and Turn In 2:00 PM DLC 270A & LRR Cards Due 11/6 4:45 AM LAUNCH DAY! 11/16 Team Meeting (work on presentation) 11/23 11/30 All Presentations and Data Due 12/4 9:00 AM DD Rev D and Team Videos Due
7
Budget Component Price (including shipping) Weight Place of Purchase
HOBO Data Logger Provided 25.0g -- Foam core Canon A570IS Digital Camera w/ Memory Card 220.0g 9V Batteries $25 101.4g Hardware Store Heater 100g Arduino USB Board (Duemilanove) $ tax 32.0g SparkFun Aluminum Tape SFE Light to Frequency Converter- TSL235R $14.75 1g Robotshop PVC Tubing Washer and Paperclip Free We have these Foam Insulation Hot Glue Velcro $5 Switches 20.0g TOTALS: PRICE: Weight: $81.60 499.4
8
Biggest Worries Inability to finish Difficulty Programming
Systems failing during the flight Not getting good pictures Biggest Worries