ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors
2
Works Contract Commencement Date: 13th June 2007
Completion Date: 31st Dec. 2009 Physical Execution: 100 % Financial Execution: 100 % WWTP became operational on 29th March 2010 1 year DNP will expire on 29th March 2011
3
WWTP Popovo - Completed
4
WWTP Popovo (during DNP and operation)
5
WWTP Popovo (during DNP and operation)
6
WWTP Popovo (during DNP and operation)
7
WWTP Popovo (during DNP and operation)
8
WWTP Popovo Publicity
9
Supervision Contract Commencement Date: 24th April 2007
Completion Date: 30th April 2011 Time elapsed: 100 % Financial Execution: 100 %
10
Compliance with Article 8 of the Financing Memorandum
Art. 8.3.a) According to EC’s letter Ref. REGIO I2/UN/ sd (2011) dated the conditions under point 8.3.a are considered as fulfilled. Art. 8.3.b) According to EC’s letter Ref. Reg12/SP/vg D/(2010)920241), dated the conditions under point 8.3.b are considered as fulfilled. Art. 8.3.c) According to EC’s letter Ref. Reg12/VN/vg D/(2011)668482), dated , the EC considers the conditions under Article 8.3.c as fulfilled.
11
Thank you for your attention!