Volusia TPO Board Meeting January 22, 2013
2
Project A: US 1 FM No: 2409922 At: Dunlawton Ave. And: Herbert St.
Year Funded: 2013; $535,000 Workmix: Intersection Improvement Phase: Construction
3
Project B: US 1 FM No: 2409925 At: Canal St. Year Funded: 2015/2018
Workmix: Intersection Improvement Phase: ROW (‘15) $1.9 million Construction (‘18) $3.4 million
4
Project C: US 1 FM No: 2409927 At: Reed Canal Rd.
Year Funded: 2015/2018 Workmix: Intersection Improvement Phase: ROW (‘15) $1.7 million Construction (‘18) $1 million
5
Project D: US 1 FM No: 2409928 At: Big Tree Rd. Year Funded: 2015/2018
Workmix: Intersection Improvement Phase: ROW (‘15) $268,000 Construction (‘18) $1 million
6
Project E: US 1 FM No: 2409929 At: LPGA Blvd.
Year Funded: $370,000 Workmix: Intersection Improvement Phase: Construction
7
Project F: SR 483 (Clyde Morris Blvd.) FM No: 4081781
From: SR 400 (Beville Rd.) To: SR 600/International Speedway Blvd. Year Funded: $28 million Workmix: Widening Phase: ROW
8
Project G: SR 472 FM No: 4336681 From: Kentucky Ave./MLK Jr. Blvd.
Kentucky Ave/MLK Blvd Project G: SR 472 FM No: From: Kentucky Ave./MLK Jr. Blvd. To: Graves Ave. Year Funded: $800,000 Workmix: Widening Phase: PD&E
9
Project H: SR 15/US 17 FM No: 4336691 From: SR 40
To: Putnam County Line Year Funded: $1.8 million Workmix: Widening Phase: PD&E
10
Project I: Alternative Analysis Study FM No: TBD
From: DeLand Sunrail Station To: Daytona Beach International Airport Year Funded: $3 million Workmix: PD&E Phase: PD&E
11
Project J: I-95 FM No: 4068696 From: North of SR 44 To: South of I-4
Year Funded: $94 million Workmix: Add Lanes & Rehabilitate Pavement Phase: Construction
12
Project K: I-95 FM No: 2427152 From: South of I-4 To: North of US 92
Year Funded: 2013 & 2016 $38.7 million Workmix: Interchange Phase: ROW
13
Work Program Public Hearing Website: