Download presentation
Presentation is loading. Please wait.
Published byStig Bech Modified over 6 years ago
1
MOM Report + RUN PLAN m. apollonio – Imperial College
November 4th 2009 MICE CM25 - RAL
2
MOMs since CM24 … Roumen Tsenov May 19 June 16 Yağmur Torun June 15
Yağmur Torun June 15 July 14 Jean-Sebastien Graulich July 13 August 7 Malcolm Ellis September 4 Linda Coney October 4 Apollonio October 9 Hanlet October 17 November 2 Cecchet November 25 (Dec 1 to be confirmed) Current MOM Blondel/Kaplan/Hanlet December 1 December 20 November 4th 2009 MICE CM25 - RAL
3
ready to RUN (Oct/Nov/Dec)
RUN (Sept/Oct) Shut Down ready to RUN (Oct/Nov/Dec) very successful period ! BL operated at full steam beam loss at high rate ACTIVATION study (*) DATA both for BL commissioning and detector calibration Q1-2-3 optimisation DKsolenoid scan many beamlines tried switched to (-) polarity for the first time … - introducing the Beam Line On Call expert (BLOC) (*) some gate/trigger problems. New measurements required Dedicated to construction/tests Target progress EPICS / Ctrl proton absorber luminosity monitor TOF0,1 calibration KL, CKOV calibration Elog ready to migrate to heplnw17 (RAL permission obtained) preparation for incoming run Get ready for User’s Run Dry Run check main functions TGT/DAQ/Detector check beam loss study TOF0,1 calib runs Q1-2-3 optim (again) OnLine Reconstruction (e,P) back to (+) polarity proton absorber machine physics u s e r s r u n November 4th 2009 MICE CM25 - RAL
4
IMPORTANT ANNOUNCEMENT ! ! !
Hi all, I spoke to Dean regarding our shifts this week: (i) There was a water failure on the Linac yesterday so the machine is still not on. Tonight's shift is at risk. (ii) Dean couldn't find shift cover for Saturday so we will be limited to 1V on Saturday. He will cover the shift on Friday so we can get up to 4 V for the high intensity study on Friday. We should plan accordingly. I will probably see you later so we can talk then. Regards, Chris November 4th 2009 MICE CM25 - RAL
5
RUN TIME (Sept / Oct 5th) November 4th 2009 MICE CM25 - RAL
6
Summary of Sept / Oct target installation and tests
Target drive installed in August shutdown Timing & depth scans during ISIS start-up to explore edge of beam Operation in ISIS MD (50 Hz/32) and User Run modes Studies of different accelerations (drive voltages) Runs at increasing target depth, producing ISIS beam-loss 0.1, 0.2, 0.3, 0.4, 0.5, 1 and 2 V (last year’s maximum for prolonged running was 50 mV) Target stability checked over long runs and between runs 62,650 pulses to date (inspections after 12, 22 & 42 k pulses) Routinely providing particles for beam-line and detector studies November 4th 2009 MICE CM25 - RAL
7
DKsolenoid has been ROUTINELY used during all previous data taking !!
Good News! After MLI insulation DKsolenoid proved its stability (successful soak test in summer) ! DKsolenoid has been ROUTINELY used during all previous data taking !! The beamline is complete !!! November 4th 2009 MICE CM25 - RAL
8
!? So we need a BeamLine On Call expert November 4th 2009
MICE CM25 - RAL
9
Beginning to calibrate TOFs Last year’s data……..This year…
TOF Calibration Beginning to calibrate TOFs Last year’s data……..This year… Making progress..need more data.. MeV/c g 2008 2009: 300 MeV/c more statistics g November 4th 2009 MICE CM25 - RAL
10
Dipping at 2V NO target Rate vs Loss in September … November 4th 2009
MICE CM25 - RAL
11
Exploring the beam edge
BCD = Beam Centre Distance Exploring the beam edge Increased depth = increased beam-loss Stable operation > 13 hours 0.2 mm (c.f. strike of 38 mm) November 4th 2009 MICE CM25 - RAL
12
Target dipping waveform
Beam Loss as a function of time Monitor depth and BL7 Target dipping waveform November 4th 2009 MICE CM25 - RAL
13
333 MeV/c pi+ beam p TOF1 TOF0 Single-channel ToF spectra
November 4th 2009 MICE CM25 - RAL
14
Proton contamination ranges out
444 MeV/c pi+ to mu+ beam Proton contamination ranges out muons! November 4th 2009 MICE CM25 - RAL
15
Excess in TOF0 largely eliminated!
444 MeV/c pi- to mu- beam Excess in TOF0 largely eliminated! muons! November 4th 2009 MICE CM25 - RAL
16
5 DK solenoid scan … Run 1121 DS current down 0.30T
Run 1122 DS current lower 0.15T M. Rayner’sTofMonitor Run 1124 DS current up 0.15T Run 1125 DS current up 0.30T November 4th 2009 MICE CM25 - RAL 5
17
reconstructed TOF tracks vs beam loss
330 MeV/c –beam reconstructed TOF tracks vs beam loss 500 mV 100 mV November 4th 2009 MICE CM25 - RAL
18
Q1-Q2-Q3 scan – US beamline optimisation
nominal config. data MC Q1-2-3 varied from nominal value Charged particles counted downstream of DKsolenoid (GVA1) Compared to MC Charged p-, m-, e- ANALYSIS MEETING TONIGHT … charged p- m- e- November 4th 2009 MICE CM25 - RAL
19
Breakdown of typical RUNS in September / October
Positive beam particles: 300 MeV/c pions target pulses (translates to about 330,000 particles used for calibrating the TOF system) 250 MeV/c pions target pulses (also for TOF) 200 MeV/c pions pulses (also for TOF) 300 MeV/c positrons target pulses (calibration of CKOV and KL calorimeter) 150 MeV/c positrons target pulses (calibration of CKOV and KL calorimeter) 330 MeV/c pions for study of Decay Solenoid effects on beam optics pulses 444 MeV/c piplus -to- muon beam to understand beam optics for producing muons pulses Pion beam at 330 MeV/c – Decay Solenoid beam dynamics study Nominal setting at 550 A (3.1 T) 9 settings higher and lower in steps of 0.15 T Only required ~60 target pulses/point to get sufficient counts in TOF0 Negative beam particles: 444 MeV/c piminus -to- muon beam Q1-2-3 scan to optimise the UpStream part of the line November 4th 2009 MICE CM25 - RAL
20
STOP (SD: Oct 6th / Nov 3rd)
November 4th 2009 MICE CM25 - RAL
21
Shut Down T2 side forces due to non-simmetries in the stator coils?
target progress Shut Down T2 side forces due to non-simmetries in the stator coils? a tough device, a tremendous effort !!! yet we need that bit to have a completely reliable system … T1 operated and BCD stability checked (400 shots) to spot possible deviations from normal behaviour (MICE-Note 270) T3 development in progress See next talk by Paul … November 4th 2009 MICE CM25 - RAL
22
Shut Down EPICS Luminosity Monitor … a near miss! Hall Infrastructure
miscellanea Shut Down EPICS Neutron monitor from MICE LCR Some little bugs fixed (sound alarm from ALH) Luminosity Monitor … a near miss! Installation postponed to next SD (practical reason) Location identified: need to finalise cabling REMINDER: installing in the ISIS vault is not ‘go & do it’ preparation & docs Hall Infrastructure November 4th 2009 MICE CM25 - RAL
23
November 4th 2009 MICE CM25 - RAL
24
Shut Down Luminosity Monitor ~20m 4.3 m 2 1 >8 m 6.3 m 3 3 ~20m
Identifying “best position” (1)-(2)-(3) are all ~20m routing from the synchrotron Paul’s best choice ~10 m from TGT ok close to wall and D1 I reckon (3) is the best match (1) has too high (rate) (2) is past the ring (does ISIS like it?) ~20m 4.3 m 2 1 >8 m 6.3 m 3 3 ~20m November 4th 2009 MICE CM25 - RAL
25
proton absorber wire control Shut Down design completed (Geoff) and device installed on Friday 30th (Roger) guillotine with 3 polyethilene blades (14, 29, 54) mm covering a range of values [14,29,…,97]mm manually operated from the turret: no access to DSA, max flexibility! proton absorber GVA1 November 4th 2009 MICE CM25 - RAL
26
READY TO START AGAIN a run plan for the month and half to come…
November 4th 2009 MICE CM25 - RAL
27
running Nov/Dec remember remember … the 6th of November 1 2 3 4
November 4th 2009 MICE CM25 - RAL
28
running Nov/Dec …run plan continued MP 5 6 7
Dean Adams Kicked Orbit test ? 8 MP Dean Adams Kicked Orbit test ? November 4th 2009 MICE CM25 - RAL
29
running Nov/Dec Quick dry run to rule out possible stoppers (MOM, JL, AD) Check BL monitoring ok Conventional BL control via EPICS ok HV for detectors ok Neutron monitor via EPICS ok DAQ (JSG) First tests tonight TARGET (PS) Re-establish basic operations tonight Run Plan for Beam Loss study delivered (Nov 6th) Permission to push losses to 4V … with strict control from ISIS CR machine physics tests November 4th 2009 MICE CM25 - RAL
30
running Nov/Dec MOM / shifter need to remember that
IMPORTANT REMINDER ! running Nov/Dec MOM / shifter need to remember that operate T1 for 5000 pulses / 8h (whichever comes first) do a Target Integrity Test (TIT) If the test is passed we can get permission for other pulses Inspect T1 window every pulses Compile Elog AND Run Conditions Summary November 4th 2009 MICE CM25 - RAL
31
PC Windows / MICE LCR November 4th 2009 MICE CM25 - RAL
32
running Nov/Dec Q1-2-3 scan
Run plan: detailed running Nov/Dec 1 Nov 10th Q1-2-3 scan Rationale: find the best 1st triplet configuration to produce PI (then MU) Vary together and/or one by one Identify a stable configuration Check results vs simulation u s e r s r u n November 4th 2009 MICE CM25 - RAL
33
running Nov/Dec Reserved for extra calibration of TOF0 and 1
TOF0,1 calibrations running Nov/Dec 2 Nov 12th Reserved for extra calibration of TOF0 and 1 Typically electron (pion) runs at 100, 150, 300 MeV/c Any request from Cherenkov ? November 4th 2009 MICE CM25 - RAL
34
(e,P) matrix running Nov/Dec Nov 17th Use TOF0,1 to characterize emittance / momentum of the beam In principle extrapolate to any position: say the diffuser Set of optics optimised to produce (a,b) and e as required to match MICE step II+ So far an exercise of optimisation based on g4beamline Is it realistic? 3 4 November 4th 2009 MICE CM25 - RAL
35
running Nov/Dec Two days required Set up and prepare the system
OnLine Reconstruction running Nov/Dec 5 Nov 23rd Two days required Set up and prepare the system Push it to high rate and check its limit November 4th 2009 MICE CM25 - RAL
36
running Nov/Dec (e,P) tests with POSITIVE beam
be positive! proton absorber tests running Nov/Dec A series of runs with POSITIVE particles Different pimu optics (at several P) Check effects of proton absorption Monitor beam shape and rate (TOF0,1 – Fermilab BPM, GVA1) (e,P) tests with POSITIVE beam Dean Adams’ kicked orbit study (date to be decided) 6 Dec 4th 7 Dec 7th 8 Dec 14th November 4th 2009 MICE CM25 - RAL
37
Hi Ken I’ ve come up with a set of orbit changes in the ring that could (if they work) steer the beam away from the target at < 8 ms by up to 10 mm. Then steer to the target from 8-9 ms by up to 10 mm and holding steady from 9-10 ms. This should hopefully give you a more beneficial spill time, deeper dip potential and save us some unnecessary beam loss. I will try to produce the orbits at some point during startup if there is time and then we could possibly have a go for real if your in agreement. Dean ms 10 mm Beam Orbit November 4th 2009 MICE CM25 - RAL
38
Summary MICE took data during all September to beginning of October after a (forced) stop of nearly 9 months successfully operated T1 for ~62K pulses beamline fully operated and being commissioned DAQ exercised Detector exercised and calibrating November 4th 2009 MICE CM25 - RAL
39
acknowledgements Thanks to … Thanks, last, to Giorgio for taking over
Linda for the nice DATA! Pierrick for subbing me! Willie for all the hard work and presence! All the shifters who kindly volunteered from now to December Thanks, last, to Giorgio for taking over good luck !!! November 4th 2009 MICE CM25 - RAL
40
M . O . M . R E P O R T November 4th 2009 TONIGHT !!! MICE CM25 - RAL
41
Beam Centre Distance stability
Dbcd=0.12 mm (stable over >10 days) November 4th 2009 MICE CM25 - RAL
42
Upstream Beam-line p! D1 ISIS synchrotron Q3 Q2 Q1 Target
November 4th 2009 MICE CM25 - RAL
43
November 4th 2009 MICE CM25 - RAL
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.