Short- and Medium-Term Scheduling Model for Large Underground Mines
Louis-Pierre Campeau and Michel Gamache Polytechnique Montreal
2
Context Planning of underground mine activities
Westwood mine, IAMGOLD, Canada Complexity in underground mine planning: Number of resources to allocate Amount of possible allocation Precedencies Congestion Precision Long-term objectives
3
Model Maximize NPV Mix of preemptive and non-preemptive
Mixed planning horizon Constraints: Equipment Capacity, Site Specific Limits, Precedencies, Backfilling, Mining Limits, Feasibility Constraints 6 years 12 months
4
Results Present: Within 5% of optimality in less than one hour of computation GUI for the use of planners Futur: Tests with different instances Comparison with manual planning Robust optimization