1 ELCITA UPDATE September 2016

2 Estate Management Skywalk E – Toilets 16 e-toilets operational.
M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E – Toilets 16 e-toilets operational. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 100 % completed. GIS Web Application Software Installed in ELCITA server. Testing work in progress.

3 Road Works – Completed Wipro Neeladri Road – Under Progress
Concrete Pavements along Doddanagamangala Village Road

4 Drain Works – Under Progress
Drain Work towards Goa Estate  Drain Work along TCS Road

5 Drain Works – Under Progress
Kerbstone work for 300KLD STP Road RCC Culvert Opp MSME Building

6 6KL capacity Sump in KIADB Ecity East Phase
Drain Works – Under Progress 6KL capacity Sump in KIADB Ecity East Phase Doddathogur Drain

7 Drain Works – Under Progress
Drain work at Celstream RCC Drain work at Ramsoft Road

8 Drain Works – Under Progress
Sewer line work Opp Canara Bank. Pavers/Drain work at Amphenol

9 Drain Works – Under Progress
Drain work at Ramakrishna Hospital SSM Drain work along Rajakaluvae to continue the Footpath

10 Drain Works – Under Progress
Drain work at JP IT Park Road Kerbstone Raising work at KSSIDC Complex

11 Drain Works – Completed
 Drain Work From Wipro Gate 5 to Wipro Gate 16  Drain Work in front of CDac 

12 Drain/Footpath Works – Completed
Removing the existing pavers & laying the new Pavers at Salarpuria Info Zone  Police Station Drain

13 Misc Works – Completed  Petty Shop Removed and covered at Tech Mahindra road Barbed Wire Fencing at Pump House

14 Misc Works – Completed  Road Widening from RS Electronics to Flextronics Road Widening at Pumphouse

15 Misc Works – Completed Replacing the existing chamber cover with RCC heavy slab with Chequer Plate.

16 Pot Hole Filling Works – Completed

17 Painting Works – Completed
Kerbstone Painting along Velankani Road, HP Avenue & Wipro Avenue etc.,

18 Sustainability Projects
RWH works – Under Progress SI.NO DESCRIPTION NO OF PITS STATUS 1 RAIN WATER HATVESTING PIT 47 COMPLETED 2 WORK IN PROGRESS

19 20 feet deep well Rainwater Harvesting Pit at Various locations

20 Estate Management Contract Awarded
Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road MSME Entry Gate to Exit Gate for 300KLD STP KSSIDC Complex Road Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road

21 Estate Management Contracts on Anvil
Providing House Keeping Services to ELCITA within Ecity Industrial Area. Providing Security Services to ELCITA within Ecity Industrial Area. Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs along XIME Road Petrol Bunk Road & Golden Tulip Road Landscaping work below fly over (Phase 1 & 2) Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2