1 Overview of Alignment Engineering Group Downtime Activities
August 2004 Overview of Alignment Engineering Group Downtime Activities Week Number Sunday Monday Tuesday Wednesday Thursday Friday Saturday 1 2 3 4 5 6 7 BABAR Survey SLM Holes Sector 20 Injector Survey Drill Anchors Survey Vacuum Components 8 9 10 11 12 13 14 BSY Injection Area Survey for 50Q1, 2 & 3 LINAC Sector 2 Align Quad 991 15 16 17 18 19 20 21 IR-10 High Energy Inject PI-11 devices Sext Offset Frascati Kicker South LTR 22 23 24 25 26 27 28 Quad Roll FFTB Beamline Alignment TFB Raft 29 30 31