be.as scheduling methods
2
Agenda Scheduling methods
1: Overview of scheduling methods provided by be.as 2: Setup and workflow 1/1/2019
3
Standard capacity planning
Standard capacity planning (included in be.as basic) Based on: routings from be.as manufacturing Scheduling direction: backward Resource types: unlimited capacity Linkage: only 1:1 (task – task) 1/1/2019
4
be.as APS be.as APS (additional module)
Based on: routings / material / tools from be.as manufacturing Direction: backward / forward Resource type: unlimited / limited capacity Linkage: only 1:1 1/1/2019
5
be.as MS-Project integration
be.as MS-Project integration (additional module) Based on: routings or operations from beas manufacturing / MSProject Direction: backward / forward Resource type: unlimited / limited capacity Linkage: n:n (e.g. End/End, Start/Start, etc.) Special features: restriction dates, diverse conditions 1/1/2019
6
Agenda Scheduling methods
1: Overview of scheduling methods provided by be.as 2: Setup and workflow 1/1/2019
7
be.as scheduling with MS-Project Parameters in be.as
Results from capacity planning in be.as are loaded into MS-Project Operations can be modified (new linking, restrictions etc.) New tasks can be added in MSProject (not relevant for production) Resources can be changed Calculation using MS-Project logic Results are written back to be.as manufacturing including extended operations in additional tables 1/1/2019
8
be.as with MS-Project scheduling Parameters in be.as
Results from capacity planning in be.as are loaded into MS-Project Operations can be modified (new linking, restrictions etc.) New tasks can be added in MSProject (not relevant for production) Resources can be changed Calculation using MS-Project logic Results are not written back to be.as manufacturing (only as information in text fields) extended operations are included in in additional tables 1/1/2019
9
be.as APS and MS-Project Parameters in be.as
Results from APS scheduling are loaded into MS-Project New tasks can be added in MSProject (not relevant for production) Resources can be changed Calculation using MS-Project logic Results are not written back to be.as manufacturing (only as information in text fields) extended operations are included in in additional tables 1/1/2019
10
Thank you for your cooperation!