Round 1 Debrief - PM What worked? What didn’t work?
Fold 1 roughly build to Takt time What didn’t work? Fold 2 takes a long time – Line Balancing Inspection takes a long time – Quality at the Source, can we inspect at the source or build to spec at station? A lot of non-value added travel time, no offense to Bubba Too many people at stamping and oven
2
Changes for Round 2 Consider the following:
Factory Layout Move tables together? Point of Use Storage (POUS) Paper at Fold 1 Line Balancing Re-distribute the work in folding? Poke-Yoke, Quality at the Source
3
Round 2 Debrief - PM What worked? What didn’t work?
Better folding balance Less tears from Frank labor reduction in stamping and ovening POUS What didn’t work? Production schedule didn’t match sales Pull system Post-it notes…do we need those?
4
Changes for Round 3 Consider the following: Factory Layout
Pull System, Kanban Continuous Flow and Supermarkets Poke-Yoke, Quality at the Source
5
Round 3 Debrief - PM What worked? What didn’t work?
Flexing folding Not scheduling/post-its Less line stress Kanban too small? What didn’t work? Shipping and Oven Kanban Looking ahead of your process Areas for improvement? Layout for oven, or different Kanban