Energy Imbalance Market
2
Energy Imbalance Market Business Practice
Part I Stakeholder Process Pre-market requirements in preparation for market simulation June 20, 2014 effective date to align with OATT revisions effective date requested at FERC Part II Stakeholder Process Remainder of EIM business practice requirements Final EIM business practice planned to be effective September 23, 2014, contingent upon FERC Order on OATT revisions Revisions to existing business practices The plan is that market sim will run from 7/7-9/12 The LMP’s will be posted publically on OASIS with a summary to the conditions that produced those LMP’s Any other “results” are really on participating specific.
3
Market Simulation Duration Goals System Testing
Market Scenario Testing Structured Scenarios Unstructured Scenarios Results Participants Non-Participants