Presentation is loading. Please wait.

Presentation is loading. Please wait.

L.Fiore Gantry Meeting during the CMS TK week

Similar presentations


Presentation on theme: "L.Fiore Gantry Meeting during the CMS TK week"— Presentation transcript:

1 L.Fiore Gantry Meeting during the CMS TK week
Bari hw status 409 r-phi frames shipped from Pisa ,to be assembled No stereo frames are available till now (only two dummies) 121 Hybrids Layer 1,2 (6 apvs) received from CERN 227 hybrids Layer3,4 (4 apvs) received from CERN 48 hybrids stereo-left received from CERN 30 hybrids stereo-right received from CERN 8 hybrids failed ARC tests 3 assembly plates for r-phi modules are operational (12 module/day production feasible) 1 assembly plate for stereo-left modules under commissioning April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week

2 Modules assembled in Bari
330 good modules were assembled till now (4 bad) 110 TIB Layer 1, phi (IB1 Sensor and 6 apv hybrid on board) 220 TIB Layer 3,4 phi (IB2 sensor and 4 apv hybrid on board) We are waiting for more r-phi hybrids to continue the assembly job Stereo hybrids shipped from CERN were ARC tested but till now were not assembled April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week

3 L.Fiore Gantry Meeting during the CMS TK week
Pictures from Bari April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week

4 L.Fiore Gantry Meeting during the CMS TK week
April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week

5 L.Fiore Gantry Meeting during the CMS TK week
April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week

6 L.Fiore Gantry Meeting during the CMS TK week
conclusions The production is going on with no big problems We will try to start the stereo module assembly as soon as possible, provided we’ll have some stereo frames The 12 modules per day is faesible but the problem is on the complete set of operations around the gantry assembly job (ARC testing,registering on db, shipping, mounting modules on the module-carrier etc..) that is now at the limit with the present man-power April 20th 2004 L.Fiore Gantry Meeting during the CMS TK week


Download ppt "L.Fiore Gantry Meeting during the CMS TK week"

Similar presentations


Ads by Google