1
In The Name of ALLAH the Most Gracious the Most Merciful
2
OPF HOUSING SCHEME ZONE-V ISLAMABAD
PROGRESS REPORT ON OPF HOUSING SCHEME ZONE-V ISLAMABAD 2
3
SEQUENCE OF PRESENTATION
Brief Overview of the Scheme Master Plan of the Scheme Details of Plots (Allotted & Vacant) Progress Update Immediate Issues New Initiatives
4
OPF Housing Scheme Zone-V, Islamabad
Location Japan Road, Zone-V, Islamabad Area 5000 Kanals Contractor Frontier Works Organization (FWO) Consultant (Design) NESPAK Consultant ( Supervision) M/s EA Consulting (Pvt) Ltd & OPF Contract Cost Rs Million Date of Start September 08, 2008 Date of Completion (Scheduled) March 07,2011 Extended Date of Completion December 30, 2015 Present Progress 98% Zone-V Briefing to Secretary OP & HRD
5
Satellite Image of the Area
OPF HOUSING SCHEME, ZONE-V, ISLAMABAD Zone-V Briefing to Secretary OP & HRD
6
OPF HOUSING SCHEME, ZONE-V, ISLAMABAD
Master Plan OPF HOUSING SCHEME, ZONE-V, ISLAMABAD To Gulberg CDA Master Plan for Zone-V (Structural Road) Access to Anchorage Blue Sqyd Off White Sq.yd Mauve Sq.yd Pink Sq.yd Yellow - Country Homes Japan Road
7
OPF HOUSING SCHEME, ZONE-V, ISLAMABAD
AERIAL VIEW BLOCK-A &B OPF HOUSING SCHEME, ZONE-V, ISLAMABAD
8
DETAIL OF PLOTS – HOUSING SCHEMES ZONE-V ISLAMABAD
Category Total Plots Allotted Vacant RESIDENTIAL 2000 Sq:Yds (100 X 180’) 1000 Sq: Yds (75 X 120’) 600 Sq: Yds (60 X 90) 355 Sq:Yds (40 X 80) 36 177 859 974 35 176 797 933 01 62 41 Total: 2046 1941 105 COMMERCIAL 100 Kanal - 100 K COUNTRY HOMES (40 X 110) K 200 APPARTMENT BLOCKS (60 X 100) 6.61 K 06
9
DETAIL OF VACANT AMENITY PLOTS OPF HOUSING SCHEME ZONE-V, ISLAMABAD
TITLE AREA (Kanals) 1. Boys school 29.50 2 Girls school 12.55 3. Boys college 44.29 4. Girls college 46.63 5. Community centre/club 80.00 6. Health centre/dispensary 35.28
10
PROGRESS UPDATE DEVELOPMENT WORKS BY FWO:
FWO has substantially completed the development works. The development works includes Road Works Sewerage Works Water supply works Drainage Works Road retaining Structure Bridge Soft landscaping Hard landscaping Services of a consultancy firm is being hired to take over the completed development works. FWO has been advised to carryout the rectification works before takeover of the scheme. FWO was also requested to carryout the development activities on 100 kanal land, possession of which was taken over on , however FWO is reluctant to take up the works.
11
PROGRESS UPDATE WATER SOURCE DEVELOPMENT:
Four overhead & four underground water reservoirs have been completed. Work on water transmission line out side the scheme along Japan Road is held up due to intervention of miscreants. A water source within the OPF Scheme area has been developed in December, 2016 having capacity of 10,000 Gallons per day to meet the initial demand of the housing scheme. As the land acquired for installation of tube wells is in litigation, the proposal have been invited for purchase of 10 kanals to 50 kanals land in the vicinity of OPF Scheme for installation of tube wells.
12
PROGRESS UPDATE ELECTRIFICATION BY IESCO:
Underground Electrification Work is in progress. Interim supply has been made available and further work on independent feeder line is in progress inside the scheme. The IESCO was requested to takeover the possession of plot (duly approved by IESCO Planning Wing) for construction of Grid station with in OPF Scheme, however, the IESCO has desired to offer substitute plot as the plot falls in depression.
13
PROGRESS UPDATE APPROACH ROAD THROUGH IBECHS:
The OPF Board approved the proposal to have access to the scheme through Gulberg Greens, a project of IBECHS. Agreement between OPF & IBECHS was signed on As per terms & conditions of the agreement OPF had transferred land measuring 804 kanal in favor of IBECHS. The IBECHS handed over provisional allotment orders of 75 residential plots measuring 500 sq. yds to OPF on During meeting of Managing Director OPF with Secretary IBECHS held on , it was agreed that IBECHS will construct the 1st access road (60 feet wide) to link OPF scheme by April 2017 and the 2nd access road of will be constructed by December, The IBECHS also agreed to issue the allotment of 76 plots (measuring 500 sq. yds. each) with plot numbers including location plan
14
PROGRESS UPDATE Construction of Boundary wall:
The work for construction of boundary wall and security posts around the OPF scheme was awarded to the contractor at a total cost of Rs million. The contractor has been mobilized at site and the construction of boundary wall and security post is being commenced within a week time. Removal of surplus soil: The work is being awarded to M/s Haji Pasham Khan & Co. at a total cost of Rs million.The work is expected to be commenced shortly.
15
APPROACH ROAD FROM GULBERG
16
Master Plan Litigation area Hatched Red 621 Kanals
17
IMMEDIATE ISSUES Handing over Possession of acquired land measuring 24 kanal-15 marla to OPF by Land Acquisition Collector/DC Islamabad for installation of tube wells is still pending. Possession of acquired land measuring 102 kanals was handed over to OPF by Land acquisition Collector, Islamabad falling within boundary of the scheme on However, the land litigants are illegally dispossessing OPF. The matter stands reported to Police authorities. Land measuring 395 kanals is under litigation in Islamabad High Court.
18
IMMEDIATE ISSUES The Prime Minister of Pakistan through Ministry of Overseas Pakistanis & HRD was requested for lifting of moratorium for provision of Suigas. In response, it has been conveyed that, provision of Sui Gas to OPF Scheme will be considered once ample supplies become available and moratorium is lifted. Agreement between OPF & IBECHS was signed on for sharing of approach road through Islamabad Expressway OPF has fulfilled its obligations by transfer of 804 Kanals land in favor of IBECHS. However, IBECHS Management has not yet fulfilled its obligation.
19
NEW INITIATIVES New Project Based Recruitments
Project Director Deputy Project Director Additional Director (Works) Land Revenue Officer Land Revenue Assistant Security Supervisor Construction of Boundary wall and 12 security posts Development of water source within scheme area Removal of surplus soil and leveling of plot areas Purchase of land for installation of tube wells Planning for handing over possession of allotted plots in selected phases
20
NEW INITIATIVES Construction of apartment buildings for allotment to the deceased / deserving Overseas Pakistanis. Construction of amenities i.e School, Mosque & Parks etc. Construction of Sewage Treatment Plant.
21
PICTURES
22
PICTURES
23
THANKS