1 SCHOOL CONSTRUCTION UPDATE Sep 7, 2016

2 OVERVIEW Review of completed projects
Update on large construction projects Update on miscellaneous projects

3 COMPLETED PROJECTS ADA Upgrades District Wide - $1.5M
Washroom Upgrade District Wide - $800K Wasilla MS/HS, Palmer HS/JMS, Houston MS, Finger Lake ES, Snowshoe ES, Butte ES, Cottonwood Creek ES, Pioneer Peak ES, Sutton ES, Tanaina ES, Willow ES , Trapper Creek ES, Admin Building roofs - $26.9M Iditarod ES - $25.2 Dena’ina ES - $26.5 Fronteras Charter School - $6.9M Ball Field Upgrades/Turf - $6.6M Athletic Complexes/Turf - $12M Mat-Su Day School - $12.4M Valley Pathways - $22.5M Big Lake ES Reno Ph I and II - $3M Houston/Palmer Jr MS Lockers - $335K Flooring Replacements Ph I and Ph II - $3M Palmer HS Mechanical Upgrades - $5.5M Swanson ES Ext Upgrades - $200K Joe Redington Sr MS/HS - $65M CTHS Addition - $16M Houston HS Exterior Siding - $600K

4 DENA’INA ES $26.5M Design: Bettisworth N. Const: FE Contracting
44,224 SF K through 5 Complete Aug 2016 Warranty Phase

5 IDITAROD ES $25.2M Design: MCG Const: Collins 50,605 SF Pre-K thru 5
Complete Aug 2016 Warranty Phase

6 FRONTERAS CHARTER SCHOOL $6.9M
Howdie Const. USDA loan and $500K from MSB Complete Aug 2016 Warranty Phase

7 ATHLETIC FIELD IMPROVEMENTS $6.4M
One baseball and one softball turf infield complete Dept. of Education approved additional work to improve access road to the fields.

8 ADDITIONAL PROJECTS District Wide Back-Up Generators $2.6M
- Wasilla MS, Big Lake ES, Butte ES, Snowshoe ES, Willow ES and Operations & Maintenance generators are complete - Wasilla HS and Palmer HS generators will be installed spring 2017 District Wide HVAC Upgrades $7.1M Phase I Contract - Control upgrades at Butte ES, Pioneer Peak ES and Snowshoe ES are complete - Control upgrades at Cottonwood ES, Finger Lake ES, Goose Bay ES and Tanaina ES are near substantial completion - New boiler at Willow ES is complete Phase II Contract - Control upgrades at Wasilla MS and Palmer JMS will continue throughout the school year - New boiler at Palmer JMS boiler is complete

9 ADDITIONAL PROJECTS cont.
District Wide Energy Upgrades (Gym Lighting and Windows) $3.1M - New LED Gym lighting project is complete - Partial window replacements at district wide locations delayed due to discovery of hazardous materials. -- Work will bid this winter for summer 2017 construction Roof Bond Balance $800K - Sutton ES roof replacement is complete - Tanaina ES roof modifications is near completion

10 QUESTIONS